PMI-ACP Exam Question 196

An agile project team has team members with varying technical skills. Due to recent events that adversely impacted customer satisfaction, management mandated that Kaizen should be given more focus to ensure the quality in product delivery.
Kaizen is a prime concept of which agile practices?
  • PMI-ACP Exam Question 197

    An agile team is working on a new product and is behind with their deliverables for the quarterly release. The team discovers new issues during each iteration. They start working on the critical issues and sometimes forget to update the backlog. This leads to confusion, delays, and occasional rework.
    How should the agile practitioner improve the team's productivity?
  • PMI-ACP Exam Question 198

    An Agile Project Lead has just been assigned to a newly formed Scrum team that is struggling to meet its initial sprint goals. To best support the team's development and performance in the early stages, which of the following actions should the Lead prioritize?
  • PMI-ACP Exam Question 199

    What should the team do?
  • PMI-ACP Exam Question 200

    A project sponsor suggested a team forgo in-person demonstration meetings and just send the product owner a link to try out the latest increment of working software. The sponsor says this will give the team more time to deliver value.
    How should the agile coach explain the importance of an in-person demonstration meeting with the sponsor?