PMI-PBA Exam Question 81
The business analyst has completed the requirements gathering and documentation processes in developing a baseline document. Several signoffs are needed. During the joint review process with the key stakeholders, the stakeholders announce that they are still not ready to sign off due to a communication gap.
Which technique should the business analyst have followed to ensure consensus?
Which technique should the business analyst have followed to ensure consensus?
PMI-PBA Exam Question 82
A major stakeholder of a project is surprised to learn that a particular requirement was not implemented during the latest launch.
The business analyst tells the stakeholder that the requirement status was changed to "deferred " What could have prevented the stakeholder from being surprised about the status change?
The business analyst tells the stakeholder that the requirement status was changed to "deferred " What could have prevented the stakeholder from being surprised about the status change?
PMI-PBA Exam Question 83
After analyzing a set of requirements documents, it is determined that the requirements are not yet ready for peer review. This was most likely caused by:
PMI-PBA Exam Question 84
A company is pleased with its delivered solution and reports that it has heard only minimal complaints for the first three months of use.
How can the business analyst determine how well the solution meets the business case?
How can the business analyst determine how well the solution meets the business case?
PMI-PBA Exam Question 85
A few months into a project, the business analyst determines that the costs are exceeding the perceived benefits. The business analyst wants to address the possible risks of having to cancel the product.
Which of the following documents should be used?
Which of the following documents should be used?