PMI-PBA Exam Question 56
A sponsor requests a new requirement The business analyst explains that most of the information needed for this requirement does not exist and that the requirement cannot be implemented. The business analyst recommends deferring the requirement until the needed information is available and then adding it to a subsequent project The sponsor agrees.
What should the business analyst do next?
What should the business analyst do next?
PMI-PBA Exam Question 57
A business analyst is assigned to the lead analyst role for a project. This project is one of the largest in the history of the company and includes several components and complex interfaces. The system in development will be used by a wide variety of stakeholders.
Which tool should the business analyst use to trace the large number of requirements that will be generated by this project?
Which tool should the business analyst use to trace the large number of requirements that will be generated by this project?
PMI-PBA Exam Question 58
A project's requirements baseline is established and approved. A stakeholder then submits a new requirement through the change control process.
How can the business analyst determine the impact on existing requirements?
How can the business analyst determine the impact on existing requirements?
PMI-PBA Exam Question 59
A business analyst has been assigned to a project team that is redesigning the company's website. The business analyst has been documenting the relationships between requirements and has found requirements that do not trace to a business need.
Which type of requirements are these?
Which type of requirements are these?
PMI-PBA Exam Question 60
A project team delivers a solution based on the approved requirements and is confident that it meets the defined acceptance criteria.
What should the business analyst do to obtain signoff?
What should the business analyst do to obtain signoff?