PMI-PBA Exam Question 126

To reduce the amount of time and effort needed to create a product specification for a project, the business analyst plans to reuse:
  • PMI-PBA Exam Question 127

    After several meetings with different groups of users, a business analyst has gathered the requirements for a large IT project. Now, the business analyst needs to document those requirements in a way that is clearly understood by the development team and provides enough information to check if the requirement has been met.
    Which of the following would work best in this case?
  • PMI-PBA Exam Question 128

    A company has just finished the development work for a new software sales tracking application and is in the process of validating that the new application meets all of the acceptance criteria defined for the business requirements. During the validation process, a stakeholder discovers that the application does not provide the selection criteria needed to produce the sales volume reporting required by the company's financial department. The business analyst for the project determines that the selection criteria needed was not specified in the system requirements or design specifications.
    Which of the following tools and/or techniques might be used by the business analyst to determine how the selection criteria requirement was missed?
  • PMI-PBA Exam Question 129

    A company is developing a new e-commerce platform to enter a new market segment. Development is well under way when the government issues a new set of regulations.
    Which course of action should the business analyst take?
  • PMI-PBA Exam Question 130

    A business analyst is trying to determine which analysis technique will be best suited to elicit information from a large number of users in a short period of time. Which elicitation technique is best suited for this purpose?