PMI-RMP Exam Question 1
Ted is the project manager of the HRR project for his company. Management has asked that Ted periodically reviews the contingency reserve as risk events happen, pass, or are still pending. What is the purpose of reviewing the contingency reserve?
PMI-RMP Exam Question 2
Lisa is the project manager of the FKN project for her organization. She is working with Sam, the CIO, to discuss a discount the vendor has offered the project based on the amount of materials that is ordered. Lisa and Sam review the offer and agree that while their project may qualify for the discounted materials the savings is nominal and they would not necessarily pursue the savings. Lisa documents this positive risk response in the risk register. What risk response is this?
PMI-RMP Exam Question 3
Donna is the project manager of the QSD Project and she believes Risk Event D in the following figure is likely to happen.

If this event does happen, how much will Donna have left in the risk contingency reserve if none of the other risk events have happened?

If this event does happen, how much will Donna have left in the risk contingency reserve if none of the other risk events have happened?
PMI-RMP Exam Question 4
You are the project manager for the ABC organization. Your current project has 75 internal stakeholders and 245 external stakeholders. Many of the risks within your project will only affect the internal stakeholders, but several of the identified risk events will affect the external stakeholders. Management would like to know the total number of communication channels in the project. How many communication channels exist in this project?
PMI-RMP Exam Question 5
Holly is the project manager of the NSS Project for her company. She is discussing some of the project risks and the issues that have happened in the project. Holly has faxed the status report to her project client for their review. Based on the standard communication model, which component in this scenario is the decoder?