PMI-RMP Exam Question 121
You are the project manager of the GHY project for your company. This project has a budget of $543,000 and is expected to last 18 months. In this project, you have identified several risk events and created risk response plans. In what project management process group will you implement risk response plans?
PMI-RMP Exam Question 122
A project team member has just identified a new project risk. The risk event is determined to have significant impact but a low probability in the project. Should the risk event happen it'll cause the project to be delayed by three weeks, which will cause new risk in the project. What should the project manager do with the risk event?
PMI-RMP Exam Question 123
There are seven risk responses, a project manager can use to address risk events. Which one of the following is a risk response that is appropriate for positive or negative risk events depending on the scenario in the project?
PMI-RMP Exam Question 124

Contingency Reserve Total: US$213,000
Due to a mitigation strategy, Risk 4's probability has been reduced to 40%. What would be the new contingency reserve total?
PMI-RMP Exam Question 125
You work as a project manager for BlueWell Inc. You would like to utilize sensitivity analysis in your project, but the management does not understand how this will be displayed. What type of chart is usually used with sensitivity analysis to show the relative affect of risks on the project?
