PMI-RMP Exam Question 11

The project manager for project X was expecting the mobilization of critical equipment from another project, project Y. However, a day before the mobilization was scheduled, another project manager notifies project X's project manager that the equipment would not be availablefor at least another month due to delayed activities for project Y. This has jeopardized meeting a critical milestone for project X.
How should project X's project manager avoid this situation in the future?
  • PMI-RMP Exam Question 12

    When conducting a risk identification exercise, what two actions should the risk manager take? (Choose two.)
  • PMI-RMP Exam Question 13

    A list of risks was identified that could occur during the design phase. Now, the team finished the design phase and those risks did not materialize.
    What should the project manager do next?
  • PMI-RMP Exam Question 14

    A project manager is working on a construction project. Based on past experience, the project manager identifies a risk that a supplier of a critical material may not deliver on time. The project manager has already accounted for this risk in the risk management plan. If this risk materializes, the project manager plans to procure the material from a different supplier. A potential risk in this plan is that there may be differences in the material provided by the first and second supplier.
    What type of risk is this?
  • PMI-RMP Exam Question 15

    A supplier Is delayed in delivering fuel for a project. The project manager anticipated this risk and is requesting fuel from another supplier. When speaking with the other supplier, a new risk appears because fulfilling the order will cause delays with several other projects.
    After performing a detailed analysis, what should the risk manager do?