PMI-RMP Exam Question 6

When processing freight invoices for a project, the project manager notices the shipping costs exceeded the budget due to increased fuel costs. The risk manager included this risk in the project's contingency allowance.
When reviewing the project budget execution reports, the project manager notices unused budget remaining in other closed tasks of the project that could cover the additional shipping costs.
What should the project manager do?
  • PMI-RMP Exam Question 7

    The risk manager is facilitating risk planning activities with the team. The team is documenting all the check points along the way that might indicate delays on critical deliverables.
    What is this an example of?
  • PMI-RMP Exam Question 8

    What is an example of legal and regulatory requirements and/or constraints when assessing a project environment for threats and opportunities?
  • PMI-RMP Exam Question 9

    As per the risk analysis process carried out for a project, two risks are registered. The probability risk A will occur is 40% and its monetary impact to the project is US$100,000. The probability risk B will occur is 60% and its monetary impact to the project is US$20,000.
    What is the total contingency budget that should be created?
  • PMI-RMP Exam Question 10

    A risk management professional is currently facilitating the risk planning process with the project team. To increase the breadth of considered risks, the team wants to include high-level and strategic project risks.
    What should the risk management professional do next?