PMP-CN Exam Question 291
一個敏捷專案正在進行六次迭代中的第二次。一位缺乏敏捷經驗的新成員剛加入團隊。在每日例會上,專案經理發現團隊在實現目標方面遇到了一些問題。
專案經理該做什麼?
專案經理該做什麼?
Correct Answer: A
According to the PMBOK Guide, 7th edition, one of the principles of project management is to collaborate with stakeholders and team members1. This principle emphasizes the importance of establishing and maintaining a shared understanding of the project vision, objectives, and expectations among all project participants. It also suggests that project managers should foster a team culture that supports collaboration, trust, learning, and adaptation1.
In an agile project, the team rules are a set of agreements that define how the team will work together, communicate, and deliver value2. The team rules should be established at the beginning of the project and reviewed periodically to ensure they are still relevant and effective2. The team rules should also be aligned with the agile values and principles, such as responding to change over following a plan and individuals and interactions over processes and tools3.
In this scenario, the project manager observes that the team is having problems meeting their goals in the second iteration. This could indicate that the team rules are not clear, not followed, or not suitable for the current situation. Therefore, the best course of action for the project manager is to provide feedback to the team and conduct a meeting to review the team rules. This will help the team to identify and resolve any issues or conflicts that are affecting their performance, and to update or modify the team rules as needed. This will also help the new team member who does not have agile experience to understand and adapt to the team's way of working.
The other options are not as effective as option A. Option B, conducting a retrospective meeting to find a root cause, is a good practice for agile teams, but it is usually done at the end of each iteration, not in the middle. A retrospective meeting is also focused on evaluating the past iteration and identifying improvement actions for the next one, not on reviewing the team rules. Option C, requesting agile training for the new member, may be helpful, but it does not address the immediate problem of the team's performance. It also assumes that the new member is the only source of the problem, which may not be true. Option D, coaching the new team member in agile methodology, is also a good practice, but it is not the primary responsibility of the project manager. The project manager should delegate the coaching task to a more experienced team member or a mentor, and focus on facilitating the team's collaboration and alignment.
1: PMBOK Guide, 7th edition, page 9 2: PMBOK Guide, 7th edition, page 95 3: Agile Manifesto, 4
In an agile project, the team rules are a set of agreements that define how the team will work together, communicate, and deliver value2. The team rules should be established at the beginning of the project and reviewed periodically to ensure they are still relevant and effective2. The team rules should also be aligned with the agile values and principles, such as responding to change over following a plan and individuals and interactions over processes and tools3.
In this scenario, the project manager observes that the team is having problems meeting their goals in the second iteration. This could indicate that the team rules are not clear, not followed, or not suitable for the current situation. Therefore, the best course of action for the project manager is to provide feedback to the team and conduct a meeting to review the team rules. This will help the team to identify and resolve any issues or conflicts that are affecting their performance, and to update or modify the team rules as needed. This will also help the new team member who does not have agile experience to understand and adapt to the team's way of working.
The other options are not as effective as option A. Option B, conducting a retrospective meeting to find a root cause, is a good practice for agile teams, but it is usually done at the end of each iteration, not in the middle. A retrospective meeting is also focused on evaluating the past iteration and identifying improvement actions for the next one, not on reviewing the team rules. Option C, requesting agile training for the new member, may be helpful, but it does not address the immediate problem of the team's performance. It also assumes that the new member is the only source of the problem, which may not be true. Option D, coaching the new team member in agile methodology, is also a good practice, but it is not the primary responsibility of the project manager. The project manager should delegate the coaching task to a more experienced team member or a mentor, and focus on facilitating the team's collaboration and alignment.
1: PMBOK Guide, 7th edition, page 9 2: PMBOK Guide, 7th edition, page 95 3: Agile Manifesto, 4
PMP-CN Exam Question 292
在第一個衝刺結束時,專案負責人注意到其中一位團隊成員的表現不太好。
專案負責人應採用哪一種溝通形式來處理這種情況?
專案負責人應採用哪一種溝通形式來處理這種情況?
Correct Answer: C
In Agile project management, especially during sprints, it is crucial to address performance issues promptly and constructively. Informal verbal communication, such as a one-on-one conversation, is often the most effective way to handle such situations. This approach allows for immediate feedback and the opportunity to discuss any obstacles the team member may be facing, as well as potential solutions. It also helps maintain a positive team dynamic and prevents the issue from escalating12.
References:
"Project Management Sprints: Methods, Steps, Best Strategies" - KnowledgeHut1.
"What is a Sprint in Project Management: Complete Guide" - Teamhood2.
References:
"Project Management Sprints: Methods, Steps, Best Strategies" - KnowledgeHut1.
"What is a Sprint in Project Management: Complete Guide" - Teamhood2.
PMP-CN Exam Question 293
專案經理注意到針對已識別問題的回應措施不足以解決問題。專案經理下一步該做什麼?
Correct Answer: D
When a project manager identifies that the response action for an issue is insufficient, it is crucial to take immediate action to prevent further complications. The best course of action in this scenario is to meet with the project team to find another solution1. This approach ensures that all team members are aware of the issue and can contribute their expertise and ideas to resolving it. It also promotes transparency and collaboration within the team1. The other options (A, B, C) are also important steps in issue management, but they are not the immediate next steps when a response action has proven to be insufficient2. References: 12
PMP-CN Exam Question 294
在一個時間緊迫的施工項目中,監理和技術員之間發生了誤會。誤會最終演變成重大衝突,技術員向專案經理投訴,表示他們無法繼續在監理手下工作。監理指出,技術員工作表現不佳是衝突的原因。專案經理該如何解決這個問題?
Correct Answer: C
According to the PMBOK Guide, conflict management is the process of identifying and addressing differences that, if left unresolved, could affect project performance1. The project manager should use appropriate conflict resolution techniques to facilitate constructive interactions among stakeholders and foster a collaborative project environment2. One of the conflict resolution techniques is collaborating, which involves incorporating multiple viewpoints and insights from different perspectives, and leads to consensus and commitment3. In the given scenario, the project manager should use a direct, collaborative approach with the technician and supervisor to understand the root cause of the conflict, address their concerns, and find a mutually acceptable solution that does not compromise the project objectives. This approach would also help to improve the relationship and trust between the technician and supervisor, and enhance their performance and motivation. References:
* 1: PMBOK Guide, 6th edition, p. 504
* 2: PMBOK Guide, 6th edition, p. 505
* 3: PMBOK Guide, 6th edition, p. 507
* 1: PMBOK Guide, 6th edition, p. 504
* 2: PMBOK Guide, 6th edition, p. 505
* 3: PMBOK Guide, 6th edition, p. 507
PMP-CN Exam Question 295
專案經理制定了與風險相關的應急計劃。風險已經顯現,但客戶堅持使用新的變通方案。客戶要求的變通方案會導致專案延誤,並需要額外的預算。專案經理該怎麼做?
Correct Answer: D
According to the PMBOK Guide, 7th edition, one of the key activities of the project manager is to engage stakeholders and manage their expectations throughout the project. This includes discussing the options with the client as part of the change control process, which is a formal and documented procedure that defines how changes to the project scope, schedule, cost, quality, or any other aspect of the project will be requested, evaluated, approved, rejected, or implemented. In this scenario, the client's request to use a new workaround instead of the approved contingency plan is a change request that may affect the project objectives and outcomes. Therefore, the project manager should discuss the options with the client as part of the change control process, and evaluate the impact, feasibility, and benefits of the proposed workaround, as well as the implications of not following the contingency plan. Option D is the best answer for this question.
Option A is not the best answer because requesting to use the management reserve to keep the schedule is not the next thing that the project manager should do. It is a possible action that the project manager may take if the change request is approved and the project budget is insufficient to cover the additional costs of the workaround, but it is not a necessary or immediate action. Moreover, requesting to use the management reserve may not always be feasible or desirable, as it may increase the project costs and risks, and may require the approval of senior management or the project sponsor.
Option B is not the best answer because mitigating risks associated with the workaround to avoid project delays is not the next thing that the project manager should do. It is a possible action that the project manager may take if the change request is approved and the workaround introduces new or increased risks to the project, but it is not a proactive or effective action to resolve the current issue. Moreover, mitigating risks may not always be possible or sufficient, as some risks may be unavoidable or unpredictable, and may require other risk response strategies, such as avoidance, transfer, or acceptance.
Option C is not the best answer because proceeding with the approved risk response plan is not the next thing that the project manager should do. It is a possible action that the project manager may take if the change request is rejected and the contingency plan is still valid and applicable, but it is not a respectful or collaborative action to deal with the client's request. Moreover, proceeding with the approved risk response plan may not always be appropriate or acceptable, as the client may have valid reasons or new information to suggest a different workaround, and may escalate the issue or withdraw their support if their request is ignored or dismissed. References: PMBOK Guide, 7th edition, pages 9-10, 15-16, 25-26, 35-36, 49-50, 59-60,
69-70.
Option A is not the best answer because requesting to use the management reserve to keep the schedule is not the next thing that the project manager should do. It is a possible action that the project manager may take if the change request is approved and the project budget is insufficient to cover the additional costs of the workaround, but it is not a necessary or immediate action. Moreover, requesting to use the management reserve may not always be feasible or desirable, as it may increase the project costs and risks, and may require the approval of senior management or the project sponsor.
Option B is not the best answer because mitigating risks associated with the workaround to avoid project delays is not the next thing that the project manager should do. It is a possible action that the project manager may take if the change request is approved and the workaround introduces new or increased risks to the project, but it is not a proactive or effective action to resolve the current issue. Moreover, mitigating risks may not always be possible or sufficient, as some risks may be unavoidable or unpredictable, and may require other risk response strategies, such as avoidance, transfer, or acceptance.
Option C is not the best answer because proceeding with the approved risk response plan is not the next thing that the project manager should do. It is a possible action that the project manager may take if the change request is rejected and the contingency plan is still valid and applicable, but it is not a respectful or collaborative action to deal with the client's request. Moreover, proceeding with the approved risk response plan may not always be appropriate or acceptable, as the client may have valid reasons or new information to suggest a different workaround, and may escalate the issue or withdraw their support if their request is ignored or dismissed. References: PMBOK Guide, 7th edition, pages 9-10, 15-16, 25-26, 35-36, 49-50, 59-60,
69-70.
- Latest Upload
- 162Cohesity.COH-285.v2026-08-22.q118
- 137Microsoft.AB-900.v2026-08-22.q35
- 274IIA.IIA-CIA-Part3.v2026-08-22.q367
- 167CheckPoint.156-315.82.v2026-08-22.q62
- 176Microsoft.GH-300.v2026-08-21.q53
- 180GIAC.GOSI.v2026-08-21.q46
- 622PMI.PMP-CN.v2026-08-21.q921
- 220Salesforce.Data-Architect.v2026-08-20.q121
- 190API.API-1184.v2026-08-20.q59
- 210Salesforce.OmniStudio-Developer.v2026-08-20.q83
[×]
Download PDF File
Enter your email address to download PMI.PMP-CN.v2026-08-21.q921 Practice Test
