PMP-CN Exam Question 381
資源管理計畫已經做好,團隊分佈在全球不同國家。團隊成員分佈在多個時區,使用不同的語言溝通。專案經理需要保持團隊井井有條,避免可能對專案產生負面影響的誤解和溝通不良。
專案經理應該怎麼做才能減少對專案的負面影響?
專案經理應該怎麼做才能減少對專案的負面影響?
Correct Answer: A
The communications management plan is a document that describes how the project information will be planned, managed, monitored, and controlled. It should include the communication requirements, methods, frequency, roles, and responsibilities of the project stakeholders. When the project team is distributed across different countries, regions, time zones, and languages, the communications management plan should be modified to address the challenges and opportunities of working in a global environment. Some of the factors that the project manager should consider are:
The cultural differences and preferences of the team members and other stakeholders, such as communication styles, norms, values, beliefs, and etiquette. The project manager should respect and appreciate the diversity of the team and avoid stereotypes, biases, and assumptions. The project manager should also use appropriate language, tone, and gestures, and avoid jargon, slang, and idioms that may cause confusion or offense. The project manager should also be aware of the potential for misunderstandings and misinterpretations due to translation errors, accents, or non-verbal cues.
The technological tools and platforms that will be used to facilitate the communication and collaboration among the team members and other stakeholders, such as email, phone, video conferencing, instant messaging, file sharing, project management software, etc. The project manager should ensure that the selected tools and platforms are accessible, reliable, secure, and compatible for all the participants. The project manager should also establish the rules and guidelines for using the tools and platforms, such as response time, frequency, format, and etiquette. The project manager should also provide training and support for the team members and other stakeholders on how to use the tools and platforms effectively and efficiently.
The time differences and schedules of the team members and other stakeholders, such as working hours, holidays, weekends, and daylight saving time. The project manager should coordinate and synchronize the communication and collaboration activities among the team members and other stakeholders, taking into account their availability and convenience. The project manager should also balance the need for synchronous and asynchronous communication, and avoid overloading or under-communicating with the team members and other stakeholders. The project manager should also respect the work-life balance and personal boundaries of the team members and other stakeholders, and avoid imposing unrealistic or unreasonable expectations or deadlines.
By modifying the communications management plan to account for regional differences, the project manager can reduce the negative impacts to the project, such as delays, errors, conflicts, misunderstandings, miscommunication, low morale, and low performance. The project manager can also enhance the positive impacts to the project, such as trust, rapport, engagement, alignment, innovation, and quality. References:
The PMI Guide to Business Analysis Includes The Standard for Business Analysis, Chapter 4: Business Analysis Planning and Monitoring, Section 4.3.3: Plan Communication Business Analysis for Practitioners: A Practice Guide, Chapter 4: Planning the Business Analysis Approach, Section 4.5: Communication Plan Business Analysis Techniques: 72 Essential Tools For Success, Chapter 6: Business Analysis Planning and Monitoring, Section 6.5: Communication Plan Seven Steps to Mastering Business Analysis, Chapter 8: Enterprise Analysis, Section 8.5: Communication Plan Research: How Cultural Differences Can Impact Global Teams, Harvard Business Review, June 9, 2021
The cultural differences and preferences of the team members and other stakeholders, such as communication styles, norms, values, beliefs, and etiquette. The project manager should respect and appreciate the diversity of the team and avoid stereotypes, biases, and assumptions. The project manager should also use appropriate language, tone, and gestures, and avoid jargon, slang, and idioms that may cause confusion or offense. The project manager should also be aware of the potential for misunderstandings and misinterpretations due to translation errors, accents, or non-verbal cues.
The technological tools and platforms that will be used to facilitate the communication and collaboration among the team members and other stakeholders, such as email, phone, video conferencing, instant messaging, file sharing, project management software, etc. The project manager should ensure that the selected tools and platforms are accessible, reliable, secure, and compatible for all the participants. The project manager should also establish the rules and guidelines for using the tools and platforms, such as response time, frequency, format, and etiquette. The project manager should also provide training and support for the team members and other stakeholders on how to use the tools and platforms effectively and efficiently.
The time differences and schedules of the team members and other stakeholders, such as working hours, holidays, weekends, and daylight saving time. The project manager should coordinate and synchronize the communication and collaboration activities among the team members and other stakeholders, taking into account their availability and convenience. The project manager should also balance the need for synchronous and asynchronous communication, and avoid overloading or under-communicating with the team members and other stakeholders. The project manager should also respect the work-life balance and personal boundaries of the team members and other stakeholders, and avoid imposing unrealistic or unreasonable expectations or deadlines.
By modifying the communications management plan to account for regional differences, the project manager can reduce the negative impacts to the project, such as delays, errors, conflicts, misunderstandings, miscommunication, low morale, and low performance. The project manager can also enhance the positive impacts to the project, such as trust, rapport, engagement, alignment, innovation, and quality. References:
The PMI Guide to Business Analysis Includes The Standard for Business Analysis, Chapter 4: Business Analysis Planning and Monitoring, Section 4.3.3: Plan Communication Business Analysis for Practitioners: A Practice Guide, Chapter 4: Planning the Business Analysis Approach, Section 4.5: Communication Plan Business Analysis Techniques: 72 Essential Tools For Success, Chapter 6: Business Analysis Planning and Monitoring, Section 6.5: Communication Plan Seven Steps to Mastering Business Analysis, Chapter 8: Enterprise Analysis, Section 8.5: Communication Plan Research: How Cultural Differences Can Impact Global Teams, Harvard Business Review, June 9, 2021
PMP-CN Exam Question 382
在衝刺計畫期間,開發主管會強調處理對產品性能至關重要的技術債任務的重要性。然而,這些任務會消耗團隊的大部分資源,導致他們無法專注於產品功能的開發。
專案經理該做什麼?
專案經理該做什麼?
Correct Answer: D
In Agile, the Product Owner is responsible for prioritizing the product backlog, which includes both features and technical work (such as reducing technical debt). If the technical debt is critical for performance, it must be addressed even at the expense of delivering new features. Once the team and Product Owner agree, these tasks should be pulled into the sprint backlog during sprint planning.
Per the Agile Practice Guide, "The product backlog may include technical work, bug fixes, and other items necessary for product health-not just features." Adding technical debt items to the sprint backlog is an accepted and necessary practice for long-term product sustainability.
References:
Agile Practice Guide, Ch. 5.4.2: "Managing Technical Debt"
Scrum Guide: Sprint Planning & Product Backlog
-
Per the Agile Practice Guide, "The product backlog may include technical work, bug fixes, and other items necessary for product health-not just features." Adding technical debt items to the sprint backlog is an accepted and necessary practice for long-term product sustainability.
References:
Agile Practice Guide, Ch. 5.4.2: "Managing Technical Debt"
Scrum Guide: Sprint Planning & Product Backlog
-
PMP-CN Exam Question 383
在每周的项目评审会议上,项目经理发现一位高级利益相关者未能及时审核和批准文件。这导致几位经验不足的初级团队成员的工作进度受到影响。
项目经理该如何解决这个问题?
项目经理该如何解决这个问题?
Correct Answer: B
This question belongs to the People domain because it focuses on stakeholder communication, approvals, and removing obstacles affecting team performance. PMI guidance notes that communication plans should define what information is needed, how it is delivered, and the roles and responsibilities around project communication and reporting. PMI also observes that delays often occur when required information or reviews are not provided on time, so these expectations should be explicitly managed.
The best response is to review the communication management plan and the approval process directly with the stakeholder . This addresses the issue at the correct level and clarifies expectations, timing, and consequences of delayed approvals. Option A focuses only on future improvement and ignores the stakeholder causing the current delay. Option C misplaces the responsibility onto junior team members.
Option D escalates too early; PMP-style logic usually favors attempting direct resolution with the stakeholder before involving the sponsor. By reviewing the process with the senior stakeholder, the project manager can reset expectations, improve turnaround times, and remove the bottleneck affecting the team.
The best response is to review the communication management plan and the approval process directly with the stakeholder . This addresses the issue at the correct level and clarifies expectations, timing, and consequences of delayed approvals. Option A focuses only on future improvement and ignores the stakeholder causing the current delay. Option C misplaces the responsibility onto junior team members.
Option D escalates too early; PMP-style logic usually favors attempting direct resolution with the stakeholder before involving the sponsor. By reviewing the process with the senior stakeholder, the project manager can reset expectations, improve turnaround times, and remove the bottleneck affecting the team.
PMP-CN Exam Question 384
供應商A的投標價格為50萬美元。該供應商有65%的可能性會延遲交付,並導致成本超支10萬美元。該供應商將提前交付,從而節省5萬美元。
專案經理應確定供應商的出價價值是多少?
專案經理應確定供應商的出價價值是多少?
Correct Answer: C
The project manager should determine the value of the vendor's bid by calculating the expected monetary value (EMV) of the bid. The EMV is the product of the probability and the impact of a risk event or opportunity1. In this case, the vendor's bid has two possible outcomes: a cost overrun of US$100,000 with a
65% probability, or a cost saving of US$50,000 with a 35% probability. The EMV of the bid is calculated as follows:
EMV = (0.65 x 100,000) - (0.35 x 50,000) = 47,500
The value of the vendor's bid is the original bid amount plus the EMV, which is:
Value = 500,000 + 47,500 = 547,500
Therefore, the correct answer is C. US$547,500.
References: (Professional in Business Analysis Reference Materials source and documents) PMBOK Guide, 6th edition, Section 11.5.2.2, "Expected Monetary Value Analysis"
65% probability, or a cost saving of US$50,000 with a 35% probability. The EMV of the bid is calculated as follows:
EMV = (0.65 x 100,000) - (0.35 x 50,000) = 47,500
The value of the vendor's bid is the original bid amount plus the EMV, which is:
Value = 500,000 + 47,500 = 547,500
Therefore, the correct answer is C. US$547,500.
References: (Professional in Business Analysis Reference Materials source and documents) PMBOK Guide, 6th edition, Section 11.5.2.2, "Expected Monetary Value Analysis"
PMP-CN Exam Question 385
在專案品質控制過程中,專案經理意識到品質管理計畫沒有包括最終使用者如何看待新產品與實際產品相比的優勢。
專案經理首先該做什麼?
專案經理首先該做什麼?
Correct Answer: C
According to the PMBOK Guide, the project quality control process consists of determining quality requirements for project deliverables and testing, inspecting and reporting to make sure they're met1. If the project manager realizes that the quality management plan does not include how the final user will perceive the benefits of the new product compared with the actual product, they should submit a change request to analyze a new set of quality tests. This is because the final user tests are part of the user acceptance testing (UAT), which is the final testing stage in software development before production2. UAT is used to get feedback from users who test the software and its user interface (UI) and to verify that the software meets the end-user requirements and expectations2. UAT is usually done manually, with users creating real-world situations and testing how the software reacts and performs2. Therefore, the project manager should not let the product go to market and wait for customer feedback regarding quality (option A), as this would be too late and risky to address any quality issues. The project manager should also not ask the quality manager or the product manager to include the final user tests in the quality management plan (options B and D), as this would be a change to the scope and the schedule of the project, which requires a formal change request and approval from the change control board3. The quality management plan is a document that helps the project manager and the project team execute quality management and quality assurance actions, and it should be aligned with the project management plan4. Any changes to the quality management plan should follow the change management process4. References: 1: Quality Control in Project Management | monday.com Blog 2:
What Is User Acceptance Testing (UAT)? - Codecademy 3: The Quality Control Process - ProjectEngineer 4:
The Quality Management Plan in Project Management
What Is User Acceptance Testing (UAT)? - Codecademy 3: The Quality Control Process - ProjectEngineer 4:
The Quality Management Plan in Project Management
- Latest Upload
- 163Cohesity.COH-285.v2026-08-22.q118
- 137Microsoft.AB-900.v2026-08-22.q35
- 275IIA.IIA-CIA-Part3.v2026-08-22.q367
- 167CheckPoint.156-315.82.v2026-08-22.q62
- 177Microsoft.GH-300.v2026-08-21.q53
- 190GIAC.GOSI.v2026-08-21.q46
- 665PMI.PMP-CN.v2026-08-21.q921
- 222Salesforce.Data-Architect.v2026-08-20.q121
- 199API.API-1184.v2026-08-20.q59
- 211Salesforce.OmniStudio-Developer.v2026-08-20.q83
[×]
Download PDF File
Enter your email address to download PMI.PMP-CN.v2026-08-21.q921 Practice Test