PfMP Exam Question 41
The portfolio management information system (PMIS) is often a collection of spreadsheets rather than automated tools. An effective PMIS enables the portfolio manager to define, analyze, design, produce, and manage systems to support a successful portfolio. Which of the following is a trait of a PMIS?
PfMP Exam Question 42
While defining the portfolio, a portfolio manager does a preliminary comparison of all inventoried portfolio components against the portfolio component definition. For this, the descriptors of each portfolio component are used in order to compare it to other components. Which of the following is not a component key descriptors?
PfMP Exam Question 43
Your company changed its executives due to the lack of benefits realization and previous corruption issues.
The new management has informed you that as of now, this will not change any process in the portfolio and everything will remain the same. However, only the risk tolerance for the organization will be impacted, what will you do as a portfolio manager?
The new management has informed you that as of now, this will not change any process in the portfolio and everything will remain the same. However, only the risk tolerance for the organization will be impacted, what will you do as a portfolio manager?
PfMP Exam Question 44
You are the manager for a governmental portfolio aiming to restructure the roads in your country. Having a tight schedule, a large number of stakeholders including the public, in addition to a strict budgeting framework, you know that you will be managing the performance closely and that the governance board and the stakeholders would want to check on the progress and performance frequently. For this you have developed a robust performance management plan. What is the expected result from developing this plan?
PfMP Exam Question 45
When it comes to change, one of your junior portfolio managers came to you requesting your help to deal with the overwhelming strategic changes. He wants your assistance in solving the issue of continuous changes in the organization's objectives. What should be your advice to him?