PfMP Exam Question 116

A number of components proposals are on the table as a result of the strategic planning cycle. While defining the portfolio, you wanted to use a method to help you compare portfolio components that address similar needs. Which of the following techniques you use?
  • PfMP Exam Question 117

    Your company acquired another company. The sponsor asked you to check the other company's current inventory of work and see what could be added to your current portfolio. You have a meeting coming up to show the sponsor the portfolio dependencies. Which document should you be showing him?
  • PfMP Exam Question 118

    You have been newly appointed as a portfolio manager and found out that your predecessor did not develop a Portfolio Risk Management plan as he thought that it is not necessary in the case where he has a risk register.
    One of your first activities was to develop the missing plan. To do this, you needed to consult with stakeholders in order to fetch risk information in order to identify risks and plan risk management. Which of the following inputs to this process will help you in identifying which stakeholders to analyze?
  • PfMP Exam Question 119

    Embracing a management-by-projects culture means there tends to be far more projects to pursue than available resources. An approach then is required to guide decisions as to components in the portfolio. A best practice to follow is to:
  • PfMP Exam Question 120

    You are the manager for a major industrial portfolio aiming to rebuild the vintage building in your region.
    Having a tight schedule, a large number of stakeholders including the public, in addition to a strict budget, you know that you will be managing the portfolio closely and that the governance board and the stakeholders would want to check on the progress and status frequently. For this you started to develop a robust Portfolio management plan. Which of the following can be used when starting this process?