PfMP Exam Question 131
Your company got recently acquired by another company and the strategic directions which your portfolio is based on have been changed. Which document do you, as a portfolio manager, update to reflect the change to the timeline?
PfMP Exam Question 132
During the portfolio lifecycle, components will be authorized, initiated, executed and closed accordingly. For authorizing the portfolio, as a program manager you will use which of the Which of the following tools and techniques?
PfMP Exam Question 133
You have already created portfolio scenarios (what-if analysis) by reviewing components against prioritization criteria and using analysis techniques (e.g., options analysis, risk analysis, SWOT analysis, financial analysis).
You now want to recommend portfolio scenario(s) and related components, based on prioritization analysis/criteria. You are doing this in order to
You now want to recommend portfolio scenario(s) and related components, based on prioritization analysis/criteria. You are doing this in order to
PfMP Exam Question 134
You are the manager for a governmental portfolio aiming to restructure the roads in your country. Having a tight schedule, a large number of stakeholders including the public, in addition to a strict budgeting framework, you know that you will be managing the performance closely and that the governance board and the stakeholders would want to check on the progress and performance frequently. For this you have developed a robust performance management plan. What is expected to be found in this plan?
PfMP Exam Question 135
As part of the portfolio communication management, multiple documents are prepared in order to effectively manage communications. The Stakeholder matrix is one of the prepared documents, what does it include?