PfMP Exam Question 101
You are managing a complex portfolio with high risk levels due to emerging technological breakthroughs and a short benefit window to market your product. You know that managing risk is key to success and you are coaching your team on the same. You are currently developing the Risk Management Plan. What can you use as inputs to this process?
PfMP Exam Question 102
When we talk about portfolios, programs and projects, it is inevitable to mention the business value which is the sum of tangible and intangible assets of an organization, also known as the net quantifiable benefit. When it comes to business value, at which level of the organization is the Business Value achieved?
PfMP Exam Question 103
Assume you are the portfolio manager for a public sector organization, and it has been part of a public-private partnership for three years for highway projects. You are making recommendations as to the next program to undertake. The head of your Highway Department in your State is questioning whether the partnership is the best approach or whether it is best to work on its own. You asked the Marketing manager for assistance, and she prepared a value-for-money analysis. This approach is useful in that it:
PfMP Exam Question 104
The portfolio strategic plan should contain a prioritization model or approach that guides the ongoing decisions as to which portfolio components should be added, terminated, or changed, as well as prioritizes and balances the component mix over time. A simple prioritization model may be provided which contains
PfMP Exam Question 105
You have scored the portfolio components and are analyzing the data in order to prioritize the components.
Using the following scoring table, which of the options represents the correct Components Priority?
Larger image
Using the following scoring table, which of the options represents the correct Components Priority?
Larger image