PgMP Exam Question 86

One of the constituent project managers asks a new program manager to obtain approval for an additional key project requirement. A tolerance range is set.
If the tolerance range is too narrow on a program, what effect will multiple minor changes have on the program?
  • PgMP Exam Question 87

    You are the program manager of the NQA Program. In this program you're planning which contract types you'll allow into the program and which ones you will not. One contract type you won't accept is the cost plus percentage of cost contract. Which of the following is a valid reason you would not allow this contract type into your program?
  • PgMP Exam Question 88

    If a program has a budget of completion of $550,000, is 25 percent complete, and has spent $135,000 what is the cost variance (CV)?
  • PgMP Exam Question 89

    You are the program manager of the NHQ Program for your organization. Your program is nearing the completion of one of its major phases and there are several resources that should be released at this time. What program management plan will guide you to release of the program resources and transfer the resources and benefits to operations within the organization?
  • PgMP Exam Question 90

    The program sponsor requests a weekly performance report. The tools and techniques to monitor and control program performance include which of the following?