PRINCE2-Foundation Exam Question 166
Which of the following statements about lines of authority and reporting are true?
1. The Project Manager has day-to-day control for a management stage within the limits laid down by the Project Board.
2. If a Team Manager forecasts a deviation beyond Work Package tolerances, this should be referred to the Project Manager.
1. The Project Manager has day-to-day control for a management stage within the limits laid down by the Project Board.
2. If a Team Manager forecasts a deviation beyond Work Package tolerances, this should be referred to the Project Manager.
PRINCE2-Foundation Exam Question 167
The senior user needs to understand how user assurance will support the senior user on the project.
PRINCE2-Foundation Exam Question 168
Which is a definition of management?
PRINCE2-Foundation Exam Question 169
Which should provide guidance on how and when prototyping is to be used?
PRINCE2-Foundation Exam Question 170
What problem may occur if projects are not aligned with corporate business strategy?