PRINCE2-Foundation Exam Question 81

Which role is responsible for ensuring the project is justified in terms of cost?
  • PRINCE2-Foundation Exam Question 82

    Which of the following statements about lines of authority and reporting are true?
    1. The Project Manager has day-to-day control for a management stage within the limits laid down by the Project Board.
    2. If a Team Manager forecasts a deviation beyond Work Package tolerances, this should be referred to the Project Manager.
  • PRINCE2-Foundation Exam Question 83

    What theme provides all management levels within the project management team with mechanisms for monitoring and control?
  • PRINCE2-Foundation Exam Question 84

    Which is a purpose of a Project Product Description?
  • PRINCE2-Foundation Exam Question 85

    Which step in the issue and change control procedure considers alternative options for responding to an issue that is being managed formally?