PRINCE2-Foundation Exam Question 81
Which role is responsible for ensuring the project is justified in terms of cost?
PRINCE2-Foundation Exam Question 82
Which of the following statements about lines of authority and reporting are true?
1. The Project Manager has day-to-day control for a management stage within the limits laid down by the Project Board.
2. If a Team Manager forecasts a deviation beyond Work Package tolerances, this should be referred to the Project Manager.
1. The Project Manager has day-to-day control for a management stage within the limits laid down by the Project Board.
2. If a Team Manager forecasts a deviation beyond Work Package tolerances, this should be referred to the Project Manager.
PRINCE2-Foundation Exam Question 83
What theme provides all management levels within the project management team with mechanisms for monitoring and control?
PRINCE2-Foundation Exam Question 84
Which is a purpose of a Project Product Description?
PRINCE2-Foundation Exam Question 85
Which step in the issue and change control procedure considers alternative options for responding to an issue that is being managed formally?