PRINCE2-Foundation Exam Question 146

Which TWO are objectives of the 'controlling a stage process?
1. To focus attention on achieving Work Within) the agree tolerances
2. To create follow on action recommendations for all open issues and risks
3. To understand how the quality required will be achieved
4. To ensure that the stage's products meet-agreed quality expectations
  • PRINCE2-Foundation Exam Question 147

    The project manager needs to monitor the progress of the stage.
    Which combination of management products should the project manager review?
  • PRINCE2-Foundation Exam Question 148

    What may be funded from a risk budget?
  • PRINCE2-Foundation Exam Question 149

    Which process should be Used to confirm that the project continues to deliver against the strategic objectives?
  • PRINCE2-Foundation Exam Question 150

    Which of the following refers to the actions identified to bring a situation to a level where exposure to a risk is acceptable?