C-TS412-1909 Exam Question 16
What functions are available for period end closing in SAP Project System? Note: There are 3 correct Answers to this question.
C-TS412-1909 Exam Question 17
You are using budgeting and active availability control. How can availability control be activated? Note:
There are 2 correct Answers to this question.
There are 2 correct Answers to this question.
C-TS412-1909 Exam Question 18
You want to use subnetworks during the project. Which of the following statements describes subnetworks?
C-TS412-1909 Exam Question 19
You have assigned a material to a network activity and want to determine the requirement date related to this activity. What set of dates do you have to maintain?
C-TS412-1909 Exam Question 20
A customer needs to analyse the capacity requirements of their network activities. Which reports do you recommend? Note: There are 2 correct Answers to this question.