C-TS422-1809 Exam Question 16
The material master of your finished product contains MRP type "PD". You set a manual firming date in the stock requirements list. Which of the following will firm planned orders" There are 2 correct answers to this question.
Response:
Response:
C-TS422-1809 Exam Question 17
What is the first step in the MRP run?
Please choose the correct answer.
Response:
Please choose the correct answer.
Response:
C-TS422-1809 Exam Question 18
A planner updated a production order status from partially confirmed "PCNF" to technically completed
"TECO" by mistake.
What impact would this have to other users for this specific production order?
Please choose the correct answer.
Response:
"TECO" by mistake.
What impact would this have to other users for this specific production order?
Please choose the correct answer.
Response:
C-TS422-1809 Exam Question 19
The SAP Kanban procedure could be used to trigger which of the following kinds of replenishment?
There are 2 correct answers to this question.
Response:
There are 2 correct answers to this question.
Response:
C-TS422-1809 Exam Question 20
In a first step you have created master recipes. In which sequence are the additional objects created?
Please choose the correct answer.
Response:
Please choose the correct answer.
Response: