C-TS422-1909 Exam Question 56

The pegging situation was changed because of an MRP heuristic run. What is a capability of dynamic pegging?
Response:
  • C-TS422-1909 Exam Question 57

    Your quality department detects a deviation in a raw material batch. Unfortunately, this batch has already been used in production. How can you identify all affected finished goods stocks?
  • C-TS422-1909 Exam Question 58

    Which of the following is an advantage of MRP Live and NOT available in classical MRP?
    Response:
  • C-TS422-1909 Exam Question 59

    You use planning strategy Finite Scheduling - with Reverse and want to allow scheduling in the past. How can you achieve this?
  • C-TS422-1909 Exam Question 60

    Which time elements are part of a routing operation? Note: There are 3 correct answers to this question.