C-TS452-1909 Exam Question 26

How does MRP Live minimize the volume of data that must be copied from the database server to the application server and back? Please choose the correct answer.
Response:
  • C-TS452-1909 Exam Question 27

    How does the system derive the company code when you post a goods movement in a plant?
    Please choose the correct answer.
    Response:
  • C-TS452-1909 Exam Question 28

    What do you need to do if you want MRP live to create planned orders for externally procured materials?
    Please choose the correct answer.
  • C-TS452-1909 Exam Question 29

    Your project requires an individual purchasing organization for each plant in your company code. What should you take into consideration when setting up such an organizational structure?
    There are 2 correct answers to this question.
    Response:
  • C-TS452-1909 Exam Question 30

    You want to manually post an initial entry of stock for a material in SAPS/4HANA. You should be able to enter both a quantity and an amount. How do you proceed?
    There are 2 correct answers to this question.