C-TSCM42-67 Exam Question 21
Which of the following items of master data are needed for repetitive manufacturing? (Choose three)
C-TSCM42-67 Exam Question 22
In SAP ECC, you calculate the standard available capacity for a work center capacity using the following data:
- Start: 7:00:00 a.m.
- End: 3:00:00 p.m.
- Break duration: 1 hour
- Rate of utilization: 80%
- Overload: 110%
- Number of individual capacities: 1
How large is the standard available capacity?
- Start: 7:00:00 a.m.
- End: 3:00:00 p.m.
- Break duration: 1 hour
- Rate of utilization: 80%
- Overload: 110%
- Number of individual capacities: 1
How large is the standard available capacity?
C-TSCM42-67 Exam Question 23
The master data for an in-house production process is to be set up in the SAP ECC system. To do this, you should create a suitable routing that plans for five operations in an initial sequence (10, 20, 30, 40, 50). There should be an option of relocating operations 30 and 40 to a second sequence on other work centers if there are capacity bottlenecks. What sequence type would you use to create the second sequence in the system?
C-TSCM42-67 Exam Question 24
Which of the following are properties of ECC Multi-Site Planning? (Choose two.)
C-TSCM42-67 Exam Question 25
An enterprise based in the US produces an end product that is used with the unit of measure "pound" (LB).
The material is now to be marketed in the EU. A prerequisite for this is that the material can be sold with the unit "kilogram" (KG).
What is the easiest way to fulfill this requirement?
The material is now to be marketed in the EU. A prerequisite for this is that the material can be sold with the unit "kilogram" (KG).
What is the easiest way to fulfill this requirement?