C_TS422_1909 Exam Question 6

You want to reduce planning efforts for B/C materials. Which planning procedure do you recommend?
  • C_TS422_1909 Exam Question 7

    During planning you are facing an overload situation on a resource. Which activities do you consider to create a feasible production plan?
    There are 3 correct answers to this question.
    Response:
  • C_TS422_1909 Exam Question 8

    Which of the following elements does MRP take into account during net requirement calculation? Note: There are 2 correct answers to this question.
  • C_TS422_1909 Exam Question 9

    How can you enhance the system statuses of a production order scenario with user statuses?
    Please choose the correct answer.
    Response:
  • C_TS422_1909 Exam Question 10

    MRP created a planned order for a material that has one single material from stock as a component. What happens to this dependent requirement when you convert the planned order into a production order?