C_TS452 Exam Question 71
A project team is validating strategic sourcing in SAP S/4HANA Cloud Private Edition for a business unit that is moving supplier negotiations out of spreadsheets and into standard system processes. Contract records were created and released in the test cycle, and buyers can view them in the web UI. However, when a purchaser creates a purchase order for materials that should be covered by an active contract, the system does not propose the contract as expected. The buyer can still finish the purchase order manually, so transaction execution is not completely blocked.
The deployment lead has imposed a constraint: the team must preserve standard contract-driven sourcing behavior, avoid manual workarounds for cutover rehearsal, and remain within clean core rules because the next transport wave already includes automated test scripts.
What should the consultant check first to resolve the upstream issue?
The deployment lead has imposed a constraint: the team must preserve standard contract-driven sourcing behavior, avoid manual workarounds for cutover rehearsal, and remain within clean core rules because the next transport wave already includes automated test scripts.
What should the consultant check first to resolve the upstream issue?
C_TS452 Exam Question 72
<strong>CHALLENGE 4 — Receipt and Invoice Consistency for Cutover Approval</strong> During final rehearsal, one depot shows stable invoice behavior for received materials and confirmed services, while another depot shows less stable invoice outcomes for comparable cases. Reviewers find that the weaker cases were prepared under different purchasing, confirmation, and responsibility assumptions. What is the best next action?
C_TS452 Exam Question 73
<strong>CHALLENGE 2 — Planning Interaction Consistency for Recurring Assembly Procurement</strong> During remediation testing, recurring assembly demand for a frequently used hydraulic subassembly appears complete at document level, but later downstream buying behavior differs between plants. Reviewers find that the earlier planning-sensitive material treatment and purchasing preparation were not combined consistently.
What should the validation team do next?
What should the validation team do next?
C_TS452 Exam Question 74
A food distribution company is validating cycle-count processing in SAP S/4HANA Cloud Private Edition across two warehouses during a phased migration from an older inventory process. Inventory documents can be created in both warehouses, and count entry is completed successfully by warehouse users. However, in the newly migrated warehouse, difference posting remains blocked for a subset of bin-managed items because the system reports that the follow-on posting status is not yet eligible, even though count results have already been recorded.
The legacy warehouse completes the same process without issue. The migration manager wants the team to keep the new warehouse on the standard process and avoid manual stock adjustments. The fix must support the migration schedule without weakening auditability or introducing local exceptions.
Which action is most appropriate?
The legacy warehouse completes the same process without issue. The migration manager wants the team to keep the new warehouse on the standard process and avoid manual stock adjustments. The fix must support the migration schedule without weakening auditability or introducing local exceptions.
Which action is most appropriate?
C_TS452 Exam Question 75
A medical-supplies distributor is validating replenishment planning in SAP S/4HANA Cloud Private Edition while retiring a legacy spreadsheet-based reorder process in two branches. Standard planning runs generate proposals correctly for most materials, and downstream purchasing tests are already underway. However, a group of branch-managed consumables transferred from the legacy process shows no proposal output after the latest planning cycle, even though demand history and stock levels would normally trigger replenishment. Materials created directly in the new model behave correctly.
The program manager wants the legacy spreadsheet retired on time. No custom planning logic may be added, and the correction must support controlled branch-by-branch modernization without extending manual replenishment longer than necessary.
Which action is most appropriate?
The program manager wants the legacy spreadsheet retired on time. No custom planning logic may be added, and the correction must support controlled branch-by-branch modernization without extending manual replenishment longer than necessary.
Which action is most appropriate?