C_TS452_2020 Exam Question 46

You are posting a goods receipt without a corresponding purchase order (PO) in the system . Which of the following are prerequisites for automatic generation of the PO at the time goods recei Note: there are 3 answer to this question
  • C_TS452_2020 Exam Question 47

    During reorder point planning, which time elements does the forward scheduling procedure take into account when calculating the availability date?
    There are 3 correct answers to this question.
    Response:
  • C_TS452_2020 Exam Question 48

    At what level do you maintain the purchasing group in the material master?
    Please choose the correct answer.
    Response:
  • C_TS452_2020 Exam Question 49

    Your purchasing department works with purchasing info records. You create a purchase order. Which logic does the system use to propose a valid price that is stored in the info record?
    There are 2 correct answers to this question.
    Response:
  • C_TS452_2020 Exam Question 50

    You test the various options that SAP S/4HANA offers for stock transfers between two different plants within the same company code.
    Which special features do stock transport orders have?
    There are 2 correct answers to this question.
    Response: