Certified-Business-Analyst Exam Question 26
The scrum team working on Salesforce projects at Northern Trail Outfitters plans to review the current build with stakeholders to gather feedback. The business analyst will facilitate the meeting.
Which type of meeting should be held?
Which type of meeting should be held?
Certified-Business-Analyst Exam Question 27
The business analyst is working with a stakeholder on a Salesforce project. The stakeholder needs an approval process on contract submissions. Sales managers want to see all contracts when the discount is greater than
20%. They will decline any contracts with a discount that is greater than 25%, but they want visibility into other highly discounted contracts.
Which acceptance criteria is the most effective for this scenario?
20%. They will decline any contracts with a discount that is greater than 25%, but they want visibility into other highly discounted contracts.
Which acceptance criteria is the most effective for this scenario?
Certified-Business-Analyst Exam Question 28
Northern Trail Outfitters (NTO) plans to significantly grow its workforce and wants to increase the overall security of its Sales Cloud instance. NTO has previously implemented a complex security solution with organization wide defaults, criteria-based sharing rules, and dozens of user profiles. NTO has asked a business analyst (0A) for recommendations on how to proceed.
Which aspect of a potential solution is most important for a BA to consider?
Which aspect of a potential solution is most important for a BA to consider?
Certified-Business-Analyst Exam Question 29
Universal Containers is implementing a Salesforce solution that's designed to transform its customer service division. During sprint planning, it was determined that the development team would be able to successfully deliver all remaining work items. However, due to unplanned delays, the development team is now at risk of being unable to complete the work items.

The project manager has asked for the business analyst's (BA) help to prioritize the remaining work items.
The development team has 16 hours of capacity remaining and is focused on launching a minimum viable product (MVP) of the customer service solution as soon as possible.
Which work items should the BA prioritize with the remaining 16 hours of development capacity?
US-4008 and US-4009

The project manager has asked for the business analyst's (BA) help to prioritize the remaining work items.
The development team has 16 hours of capacity remaining and is focused on launching a minimum viable product (MVP) of the customer service solution as soon as possible.
Which work items should the BA prioritize with the remaining 16 hours of development capacity?
US-4008 and US-4009
Certified-Business-Analyst Exam Question 30
The business analyst at Universal Containers is writing users stories to support the Salesforce implementation for the sales operations division.
There is a request for visibility into sales rep' pipeline so that can see their revenue.
Which missing component is necessary to finish this user story?
There is a request for visibility into sales rep' pipeline so that can see their revenue.
Which missing component is necessary to finish this user story?