SMC Exam Question 56
A Scrum Team wants to conduct a meeting in which they plan to deliberate on ways to improve team collaboration and effectiveness in future. This can be identified as which type of meeting?
SMC Exam Question 57
Mark is the Product Owner and he asks you, the Scrum Master what burndown charts actually track. What's the best response for Mark?
SMC Exam Question 58
Program Stakeholders, the Program Product Owner, Program Scrum Master, and Chief Product Owner have gathered together to create the Project Vision. They are trying to determine and document the difference between current business capabilities and the final desired set of capabilities. Which one of the following should they use to arrive at aconclusive decision?
SMC Exam Question 59
To enable collaboration, the Product Owner, the Scrum Master, and the Scrum Team collaborate with each other and the stakeholders to create deliverables that provide the greatest possible value to the customer.
This ensures realization of all the following project benefits, EXCEPT:
This ensures realization of all the following project benefits, EXCEPT:
SMC Exam Question 60
Which one of the following is NOT a type of identified dependencies in a Scrum project?