Your role is that of a consultant to the Lead Enterprise Architect in a company that develops photovoltaic technologies for use in large-scale solar power farms. The company has three manufacturing facilities, two in the United States, and one in Southern France. Each of these facilities supplies a different manufacturer that assembles and sells complete systems. The solar panels and photovoltaic arrays are custom engineered to meet each manufacturer's design specifications.
A challenge that the solar power industry has faced is the efficiency of energy conversion. When a conventional solar panel overheats, it becomes inefficient and generates less energy. In response to this, the research arm of the company has pioneered the development of a new solar panel design that will produce up to 50% more energy than standard solar panels when operating at elevated temperatures.
This will allow the production of significantly more useable energy per square meter than from standard solar technology. This new design is ready to go into production.
The company has a mature Enterprise Architecture practice that is supported by a cross-functional Architecture Board. TOGAF 9 is used for developing the automated manufacturing process and systems used to design, manufacture and test the solar power technologies they produce. The Chief Information Officer and the Chief Operating Officer co-sponsor the Enterprise Architecture program.
As part of putting the new solar panel design into production, a pilot architecture project at a single location has defined an updated standard approach for controlling the automated test systems used to perform final quality assurance. The Chief Engineer, sponsor of the activity, and the Architecture Board have approved the plan for immediate implementation at each plant.
Architecture Contracts have been developed that detail the work needed to implement and deploy the new automated test system controller for each location. The Chief Engineer has expressed concern that a uniform process be employed at each location to ensure consistency and high yields.
Refer to the Scenario
The Lead Enterprise Architect has asked you to recommend the best approach to address the Chief Engineer's concern.
Based on TOGAF, which of the following is the best answer?
Please read this scenario prior to answering the question
Your role is that of a consultant to the Lead Enterprise Architect in a company that develops photovoltaic technologies for use in large-scale solar power farms. The company has three manufacturing facilities, two in the United States, and one in Southern France. Each of these facilities supplies a different manufacturer that assembles and sells complete systems. The solar panels and photovoltaic arrays are custom engineered to meet each manufacturer's design specifications.
A challenge that the solar power industry has faced is the efficiency of energy conversion. When a conventional solar panel overheats, it becomes inefficient and generates less energy. In response to this, the research arm of the company has pioneered the development of a new solar panel design that will produce up to 50% more energy than standard solar panels when operating at elevated temperatures.
This will allow the production of significantly more useable energy per square meter than from standard solar technology. This new design is ready to go into production.
The company has a mature Enterprise Architecture practice that is supported by a cross-functional Architecture Board. TOGAF 9 is used for developing the automated manufacturing process and systems used to design, manufacture and test the solar power technologies they produce. The Chief Information Officer and the Chief Operating Officer co-sponsor the Enterprise Architecture program.
As part of putting the new solar panel design into production, a pilot architecture project at a single location has defined an updated standard approach for controlling the automated test systems used to perform final quality assurance. The Chief Engineer, sponsor of the activity, and the Architecture Board have approved the plan for immediate implementation at each plant.
Architecture Contracts have been developed that detail the work needed to implement and deploy the new automated test system controller for each location. The Chief Engineer has expressed concern that a uniform process be employed at each location to ensure consistency and high yields.
Refer to the Scenario
The Lead Enterprise Architect has asked you to recommend the best approach to address the Chief Engineer's concern.
Based on TOGAF, which of the following is the best answer?
OG0-092 Exam Question 38
Scenario:
Please read this scenario prior to answering the Question
You have been assigned the role of Lead Enterprise Architect for a manufacturing firm that specializes in musical instruments. The firm has been established for over 100 years, operating in North America for most of that time. In the last ten years, the firm has expanded into European markets and will soon establish a market in Latin America. A future expansion into the Asia Pacific region is also planned.
The firm is organized into several business units that each focus on manufacturing particular families of instruments such as brass, woodwind, and percussion. Each business unit has acquired other producers to expand its manufacturing capacity. This has resulted in a complex environment with a high diversity of business and manufacturing systems.
The Enterprise Architecture (EA) program within the firm has been functioning for several years. It has made significant progress in consolidating the technology portfolio and establishing key standards. The CIO and the COO are pint sponsors of the EA program. The EA program is mature, with an active Architecture Board and a well-defined architecture process and standard content templates based on the TOGAF 9 Architecture Content Framework. The EA process framework is well coordinated with the PMO, Systems Development, and Operations functions.
The firm has completed a strategic plan to reorganize its Sales & Marketing organization according to the four target geographic markets. One of the goals of this reorganization is to improve the ability of Marketing to collect more meaningful market analytics that will enable each sector to better address market needs with effective marketing campaigns and global product presence.
A Request for Architecture Work to address the goals of the reorganization has been approved. As the architecture team commences its work, the CIO has expressed concerns about whether the firm will be able to adapt to the proposed architecture and how to manage the associated risks.
Refer to the Scenario
You have been asked how to address the concerns of the CIO.
Based on TOGAF 9, which of the following is the best answer?
Please read this scenario prior to answering the Question
You have been assigned the role of Lead Enterprise Architect for a manufacturing firm that specializes in musical instruments. The firm has been established for over 100 years, operating in North America for most of that time. In the last ten years, the firm has expanded into European markets and will soon establish a market in Latin America. A future expansion into the Asia Pacific region is also planned.
The firm is organized into several business units that each focus on manufacturing particular families of instruments such as brass, woodwind, and percussion. Each business unit has acquired other producers to expand its manufacturing capacity. This has resulted in a complex environment with a high diversity of business and manufacturing systems.
The Enterprise Architecture (EA) program within the firm has been functioning for several years. It has made significant progress in consolidating the technology portfolio and establishing key standards. The CIO and the COO are pint sponsors of the EA program. The EA program is mature, with an active Architecture Board and a well-defined architecture process and standard content templates based on the TOGAF 9 Architecture Content Framework. The EA process framework is well coordinated with the PMO, Systems Development, and Operations functions.
The firm has completed a strategic plan to reorganize its Sales & Marketing organization according to the four target geographic markets. One of the goals of this reorganization is to improve the ability of Marketing to collect more meaningful market analytics that will enable each sector to better address market needs with effective marketing campaigns and global product presence.
A Request for Architecture Work to address the goals of the reorganization has been approved. As the architecture team commences its work, the CIO has expressed concerns about whether the firm will be able to adapt to the proposed architecture and how to manage the associated risks.
Refer to the Scenario
You have been asked how to address the concerns of the CIO.
Based on TOGAF 9, which of the following is the best answer?
OG0-092 Exam Question 39
Scenario
Please read this scenario prior to answering the question
You have been assigned the role of Chief Enterprise Architect within a leading outsourcing services company.
The company has over 15,000 outsourcing professionals and works on some of the world's largest outsourcing
projects. Outsourcing services include business processes, infrastructure, and service management. The
company also provides business consulting services. Roughly half of its turnover comes from the private sector
and half from the public sector.
With numerous service areas and a large number of diverse engagements in progress at any given time,
overall engagement management within the company has become challenging. The company has recently had
a number of high profile projects that have overrun on budget and under delivered, thereby damaging its
reputation.
The company has an established an Enterprise Architecture program based on TOGAF 9, sponsored jointly by
the Chief Executive Officer and Chief Information Officer. An Architecture Board has been formed comprised
of IT staff executives and executives from the major service areas and consulting practice.
The Enterprise Architecture (EA) team has been working with the Strategic Planning team to create a strategic
enterprise architecture to address these issues. The EA team has defined a framework and held workshops
with key stakeholders to define a set of architecture principles to govern the architecture work. They have
completed an Architecture Vision at a strategic level and laid out Architecture Definitions for the four domains.
They have set out an ambitious vision of the future of the company over a five-year period. This will include
three distinct transformations.
The CIO has made it clear that prior to the approval of the detailed implementation and Migration plan, the EA
team will need to assess the risks associated with the proposed architecture. He has received concerns from
some of the vice presidents across the company that the proposed architecture may be too ambitious and they
are not sure it can produce sufficient value to warrant the attendant risks.
Refer to the Scenario
You have been asked to recommend an approach to satisfy these concerns.
Based on TOGAF, which of the following is the best answer?
Please read this scenario prior to answering the question
You have been assigned the role of Chief Enterprise Architect within a leading outsourcing services company.
The company has over 15,000 outsourcing professionals and works on some of the world's largest outsourcing
projects. Outsourcing services include business processes, infrastructure, and service management. The
company also provides business consulting services. Roughly half of its turnover comes from the private sector
and half from the public sector.
With numerous service areas and a large number of diverse engagements in progress at any given time,
overall engagement management within the company has become challenging. The company has recently had
a number of high profile projects that have overrun on budget and under delivered, thereby damaging its
reputation.
The company has an established an Enterprise Architecture program based on TOGAF 9, sponsored jointly by
the Chief Executive Officer and Chief Information Officer. An Architecture Board has been formed comprised
of IT staff executives and executives from the major service areas and consulting practice.
The Enterprise Architecture (EA) team has been working with the Strategic Planning team to create a strategic
enterprise architecture to address these issues. The EA team has defined a framework and held workshops
with key stakeholders to define a set of architecture principles to govern the architecture work. They have
completed an Architecture Vision at a strategic level and laid out Architecture Definitions for the four domains.
They have set out an ambitious vision of the future of the company over a five-year period. This will include
three distinct transformations.
The CIO has made it clear that prior to the approval of the detailed implementation and Migration plan, the EA
team will need to assess the risks associated with the proposed architecture. He has received concerns from
some of the vice presidents across the company that the proposed architecture may be too ambitious and they
are not sure it can produce sufficient value to warrant the attendant risks.
Refer to the Scenario
You have been asked to recommend an approach to satisfy these concerns.
Based on TOGAF, which of the following is the best answer?
OG0-092 Exam Question 40
Scenario:
Please read this scenario prior to answering the question
Your role is consultant to the Lead Architect within a company that manufactures a variety of small electromechanical devices. As part of a corporate-wide Lean Manufacturing initiative, the company has defined a strategic architecture to improve its ability to meet consumer demand and improve its ability to manage its supply chain. The strategic architecture called for the consolidation of multiple Enterprise Resource Planning (ERP) applications that have been operating independently in several of the divisions' production facilities. The goal is to replace the functionality of the existing applications with a new ERP product running as a single instance in the company's primary data center.
The company has a mature enterprise architecture practice and uses TOGAF 9 for the basis of its architecture framework. In addition to the EA program, the company has a number of management frameworks in use, including business planning, portfolio/project management, and operations management. The EA program is sponsored by the CIO.
Each division has completed the Architecture Definition documentation required to tailor and configure the environment to meet its own specific manufacturing requirements.
The enterprise architects have analyzed the key corporate change attributes and implementation constraints. A consolidated gap analysis has been completed which has identified the gaps across the Business, Data, Application, and Technology domains. Based on the results of the gap analysis, the architects have reviewed the requirements, dependencies and interoperability requirements needed to integrate the new ERP environment into the existing environment. The architects have completed the Business Transformation Readiness Assessment started in Phase
Please read this scenario prior to answering the question
Your role is consultant to the Lead Architect within a company that manufactures a variety of small electromechanical devices. As part of a corporate-wide Lean Manufacturing initiative, the company has defined a strategic architecture to improve its ability to meet consumer demand and improve its ability to manage its supply chain. The strategic architecture called for the consolidation of multiple Enterprise Resource Planning (ERP) applications that have been operating independently in several of the divisions' production facilities. The goal is to replace the functionality of the existing applications with a new ERP product running as a single instance in the company's primary data center.
The company has a mature enterprise architecture practice and uses TOGAF 9 for the basis of its architecture framework. In addition to the EA program, the company has a number of management frameworks in use, including business planning, portfolio/project management, and operations management. The EA program is sponsored by the CIO.
Each division has completed the Architecture Definition documentation required to tailor and configure the environment to meet its own specific manufacturing requirements.
The enterprise architects have analyzed the key corporate change attributes and implementation constraints. A consolidated gap analysis has been completed which has identified the gaps across the Business, Data, Application, and Technology domains. Based on the results of the gap analysis, the architects have reviewed the requirements, dependencies and interoperability requirements needed to integrate the new ERP environment into the existing environment. The architects have completed the Business Transformation Readiness Assessment started in Phase
OG0-092 Exam Question 41
Scenario: Raxlon Inc.
Case Study Title (Case Study):
Raxlon Inc. is a Fortune 500 Company dealing in high value drugs and pharma products. Its annual turnover is over 120 billion $. It has more than 100,000 employees all over the globe in its R&D, Manufacturing and Marketing Units.
Raxlon's CEO, Dr Peter Fowles, is a pharmacology expert and has over 72 patents on various types of drugs mainly used for treating patients with genetic disorders. Raxlon is now moving into a suite of high end critical drug products used for Genetic Repair of congenital Diseases like Alzhmeir's disease and Epilepsy. Rexlon has a well developed EA practice and in 2009 the EA practice has adopted TOGAF 9 as the primary Framework for Enterprise Architectural Change Agent.
Dr Fowles' main concerns are:
Security of the critical data which they have gained over the years after painstaking research. Although Rexlon had an adequate security system Dr Fowles feels it may not be adequate to deal with the new order of things, especially with data which is highly confidential and if leaked would have major financial impact on the Company.
Dr Fowles calls his CIO and explains his position to him and entrusts whim with the responsibly of evaluating the current security system, operation and governance and determine which are the gaps which need to be addressed during the fresh architectural work. Assume that a new Security Framework would be used in the ADM life cycle. To protect Rexlon's valuable IP.
The CIO apprises the Lead Architect of the sensitive nature of the work he has to complete within the next 2 months.
Identify which of the following processes would be most appropriate for the Lead Architect to adopt in this situation.
Case Study Title (Case Study):
Raxlon Inc. is a Fortune 500 Company dealing in high value drugs and pharma products. Its annual turnover is over 120 billion $. It has more than 100,000 employees all over the globe in its R&D, Manufacturing and Marketing Units.
Raxlon's CEO, Dr Peter Fowles, is a pharmacology expert and has over 72 patents on various types of drugs mainly used for treating patients with genetic disorders. Raxlon is now moving into a suite of high end critical drug products used for Genetic Repair of congenital Diseases like Alzhmeir's disease and Epilepsy. Rexlon has a well developed EA practice and in 2009 the EA practice has adopted TOGAF 9 as the primary Framework for Enterprise Architectural Change Agent.
Dr Fowles' main concerns are:
Security of the critical data which they have gained over the years after painstaking research. Although Rexlon had an adequate security system Dr Fowles feels it may not be adequate to deal with the new order of things, especially with data which is highly confidential and if leaked would have major financial impact on the Company.
Dr Fowles calls his CIO and explains his position to him and entrusts whim with the responsibly of evaluating the current security system, operation and governance and determine which are the gaps which need to be addressed during the fresh architectural work. Assume that a new Security Framework would be used in the ADM life cycle. To protect Rexlon's valuable IP.
The CIO apprises the Lead Architect of the sensitive nature of the work he has to complete within the next 2 months.
Identify which of the following processes would be most appropriate for the Lead Architect to adopt in this situation.