OGEA-103 Exam Question 61

Refer to the table below:

Which ADM Phase does this describe?
  • OGEA-103 Exam Question 62

    Consider the following descriptions of deliverables consumed and produced across the TOGAF ADM cycle.
    General rules and guidelines, intended to be enduring and seldom amended, that inform and support the way in which an organization sets about fulfilling its mission
    The joint agreements between development partners and sponsors on the deliverables, quality, and fitness-for-purpose of an architecture.
    A document that is sent from the sponsoring organization to the architecture organization to trigger the start of an architecture development cycle
    A set of quantitative statements that outline what an implementation project must do in order to comply with the architecture.
    Which deliverables match these descriptions?
  • OGEA-103 Exam Question 63

    Which deliverable is first produced in Phase A, also updated in Phase E, and helps the architect to understand the baseline and target for the enterprise?
  • OGEA-103 Exam Question 64

    Consider the following ADM phase objectives.
    #
    Objective
    1
    Determine whether an incremental approach is required, and if so identify Transition Architectures that will deliver continuous business value
    2
    Generate the initial complete version of the Architecture Roadmap, based upon the gap analysis and candidate Architecture Roadmap components from Phases B, C, and D
    3
    Finalize the Architecture Roadmap and the supporting Implementation and Migration Plan
    4
    Ensure that the business value and cost of work packages and Transition Architectures is understood by key stakeholders Which two are objectives of ADM Phase F?
  • OGEA-103 Exam Question 65

    What component of the Architecture Repository represents architecture requirements agreed with the Architecture Board?