Question 1

For the DEV project, Max has these requirements relating to time logging:
* I need to be able to edit time logs.
* I need to be able to delete time logs.
Which three project permissions does Max need in order to meet these requirements? (Choose three.)

Question 2

Martina is unable to perform the following actions in the App project:
* Create and manage versions
* Create and manage components
* Rank issues in the backlog
The App project does not use a shared permission scheme.
Which two permissions will allow her to perform those actions? (Choose two.)

Question 3

Teresa is able to see the Start Progress transition but not the Approve transition on an issue. Her co-worker is able to see both.
Identify two possible causes why Teresa can NOT see the Approve transition. (Choose two.)

Question 4

Tom needs to work on scheduling and reordering future Sprints in a project.
What are the minimum two permissions that Tom needs? (Choose two.)

Question 5

All users should be able to transition issues in your project without restrictions.
However, some users complain that they cannot transition issues to the In Progress status. They can execute other transitions.
The workflow is shown below.

What should you request from the Jira administrator?