A project is assigned to a qualified project manager by the program manager I he client rejects the project manager due to a lack of proper qualifications to manage such a project
What should the program manager do next?
A program is in its execution phase when a component project manager suggests a potential change that could increase the financial benefit of the program. The program manager is hesitant to submit a change request, as it would extend the program schedule and require a scope change.
To whom should the change request be presented?