PK0-004 Exam Question 166

A senior developer abruptly resigned without notice. Because of the senior developer's expertise, the active task workload was substantial.
This would MOST likely impact the project's: (Choose two.)
  • PK0-004 Exam Question 167

    Due to a new government regulation, a project change is required. The project manager evaluates the change and realizes a representative from the legal department will need to approve the change as well.
    The project manager should:
  • PK0-004 Exam Question 168

    A project manager is attempting to establish the proper sequencing and duration of project activities. Which of the following would be the MOST beneficial?
  • PK0-004 Exam Question 169

    The PMO has asked the PM to provide a status report indicating the number of events and activities required to complete a project. Which of the following charts should the PM include in the status report?
  • PK0-004 Exam Question 170

    A project manager has an opportunity to add a highly skilled expert to the team who can increase the probability of the project's success.
    Which of the following risk strategies should the project manager adopt?