PK0-004 Exam Question 171

Which of the following documents should be used to provide high-level reporting to key stakeholders?
  • PK0-004 Exam Question 172

    A project manager has noticed poor attendance as status meetings.
    Which of the following strategies should the project manager use to improve attendance?
    (Choose two.)
  • PK0-004 Exam Question 173

    A new high-priority project is assigned to the project manager with a fully formed budget, deadline, and scope. The project manager is creating the project schedule.

    Which of the following calculations accurately shows the critical path?
  • PK0-004 Exam Question 174

    A project is coming to the end of a phase. The PMO required that the quality team review the work and budget before moving on to the next phase of the project. The project manager must schedule the review of the phase and have the stakeholders present. This review is referred to as:
  • PK0-004 Exam Question 175

    There are four parallel paths on a network diagram. The summary duration of each path is below:
    A, C, G: 10 weeks
    A, B, F: 8 weeks
    D, E, H: 12 weeks
    D, B, F: 7 weeks
    Which of the following tasks are on the critical path?