PK0-004 Exam Question 196
A non-stakeholder approaches the project manager and asks if certain items can be added to a project that was started two months earlier. Which of the following constraints does this impact MOST?
PK0-004 Exam Question 197
A project is taking more effort than anticipated. Which of the following constraints will MOST likely be affected?
PK0-004 Exam Question 198
A project's key stakeholders have requested significant changes that will affect the scope.
To adjust the project scope, which of the following need to be changed? (Choose two.)
To adjust the project scope, which of the following need to be changed? (Choose two.)
PK0-004 Exam Question 199
Which of the following describes risk mitigation?
PK0-004 Exam Question 200
Which of the following project phases occurs when requirements are detailed?