PK0-004 Exam Question 96
A team lead informs the project manager that the datacenter will not be accessible when the project needs to be completed. The team lead also indicates that the team member who is assigned to complete the datacenter project is out on medical leave.
Which of the following should a project manager update to document this information?
Which of the following should a project manager update to document this information?
PK0-004 Exam Question 97
Despite receiving regular updates, a sponsor learns a project recently slipped.
Which of the following documents can the sponsor review to determine the project's performance? (Select two.)
Which of the following documents can the sponsor review to determine the project's performance? (Select two.)
PK0-004 Exam Question 98
In which of the following categories does a business process change fit?
PK0-004 Exam Question 99
A project requires daily status updates.
Which of the following is the MOST effective method for providing these updates?
Which of the following is the MOST effective method for providing these updates?
PK0-004 Exam Question 100
A task on the critical path has just been completed. The project manager has been informed that the person responsible for the next task has gone on an approved leave. Which of the following types of organizational structure does this scenario BEST describe?