PK0-004 Exam Question 101
During the execution phase of a project, a project task has run longer than anticipated.

Which of the following is the new critical path of the project if Task 2 requires an additional two days to complete?

Which of the following is the new critical path of the project if Task 2 requires an additional two days to complete?
PK0-004 Exam Question 102
A project manager is mapping qualifications and available personnel to the project requirements. Which of the following activities is the project manager completing?
PK0-004 Exam Question 103
Which of the following project documents should be used to record the occurrence of an unplanned event?
PK0-004 Exam Question 104
Which of the following is a schedule that illustrates the duration of an activity?
PK0-004 Exam Question 105
While developing a project schedule, the project manager is attempting to sequence the following tasks:

Which of the following is the correct sequence for the above tasks?