PK0-004 Exam Question 36

Company A and Company B have come together to form a new Company C.
Staff members from both companies have been moved to Company C, and there are rumors that some staff might be asked to leave.
These are examples of: (Choose two.)
  • PK0-004 Exam Question 37

    A project manager has an opportunity to add a highly skilled expert to the team who can increase the probability of the project's success.
    Which of the following risk strategies should the project manager adopt?
  • PK0-004 Exam Question 38

    A project manager is assigned to a new project that must start immediately. No formal or approved documents have been authored for the project. The project manager must identify project roles, justify the business need, and determine project scope boundaries.
    Which of the following documents should the project manager create?
  • PK0-004 Exam Question 39

    Which of the following metrics demonstrates to a project manager if a project is overspending or underspending?
  • PK0-004 Exam Question 40

    A project team is composed of numerous team members who are located throughout a country. All personnel have identified core business hours. A team engineer based in a machine shop has a question during business hours for the project manager, who is located at a different facility.
    Which of the following is the MOST expedient communication method, assuming the question can be resolved quickly?