PK0-004 Exam Question 31

During a project, the project manager discovers there is insufficient time allotted for quality control. The project manager prepared to submit a revised schedule to the CCB.

Given the attached chart, which of the following is the critical path if one day is added to each task for quality control?
  • PK0-004 Exam Question 32

    А new stakeholder has been added to a project with a BAG of $850,000. The stakeholder has raised five change requests to the CCB; two of them have been approved, and three are awaiting initial review.
    Considering the project has a CPI of 0.89 and an SPI of 1.14, and the approved ones will be implemented, which of the following should the project manager do LAST?
  • PK0-004 Exam Question 33

    In a project with a of $235,000, the CPI is 0.80, and the SPI is 1.20. Based on this information, which of the following can the key stakeholders determine about the project?
  • PK0-004 Exam Question 34

    A project manager is assigned to a project that was previously managed by a peer project manager. The project manager identifies several modifications that were deployed prior to CCB approval. Which of the following change control processes is being mismanaged?
  • PK0-004 Exam Question 35

    A project team member highlights to the project manager that expensive licensing for critical software in use across the project may expire before the completion project.
    Which of the following would the project manager MOST likely do?