ASM Exam Question 1

A Development Team consists of various different roles: analysts, programmers, UX experts, DBA and systems architects. They are estimating Backlog Items in Ideal Days.
What is the best approach to provide estimates for the Backlog Items?
  • ASM Exam Question 2

    Scrum Master is the 'servant leader' of Scrum Team. In this context, which of the following is a key responsibility of the Scrum Master?
  • ASM Exam Question 3

    A company is transitioning to working with Scrum Adnana was working as the project manager but will now take on the role of Scrum Master She will be working with new co-workers In the Scrum team Which project management activity or activities will Adnana keep doing as the Scrum Master of the new team?
  • ASM Exam Question 4

    Which of the following is the correct format for writing a User Story?
  • ASM Exam Question 5

    During a Sprint Planning, a team has picked three User Stories:
    Story 1 - 5 Story Points
    Story 2 - 8 Story Points
    Story 3 - 3 Story Points
    At the end of the Sprint, the team has completed Story 1 and Story 3 and the Product Owner accepts these.
    The team has almost completed Story 2 but there are a few bugs identified in acceptance tests.
    What is the Velocity of this team?