HPE0-J82 Exam Question 26
A Disaster Recovery Architect is reviewing a proposed replication design for a healthcare provider.
Requirements:
RPO = 0
RTO < 10 minutes
Datacenter Separation: 20 km
Automated failover
VMware vSphere
Current Proposal:
Asynchronous replication every 15 minutes
Manual recovery procedures
Independent storage presentation at DR site
Which THREE concerns should be raised regarding the proposal? (Choose 3.)
Requirements:
RPO = 0
RTO < 10 minutes
Datacenter Separation: 20 km
Automated failover
VMware vSphere
Current Proposal:
Asynchronous replication every 15 minutes
Manual recovery procedures
Independent storage presentation at DR site
Which THREE concerns should be raised regarding the proposal? (Choose 3.)
HPE0-J82 Exam Question 27
An HPE InfoSight predictive analytics report identifies a rapidly deteriorating capacity forecast.
[Capacity Forecast Dashboard]
Physical Capacity Used: 560 TB
Physical Capacity Free: 34 TB
Forecasted Exhaustion: 21 Days
Application Growth: 0.9 TB/Month
Snapshot Growth: 24 TB/Month
Recent Changes:
Immutable Snapshot Policy Enabled
Retention Increased from 14 Days to 365 Days
Ransomware Protection Policy Applied
Which THREE conclusions are supported by the available telemetry? (Choose 3.)
[Capacity Forecast Dashboard]
Physical Capacity Used: 560 TB
Physical Capacity Free: 34 TB
Forecasted Exhaustion: 21 Days
Application Growth: 0.9 TB/Month
Snapshot Growth: 24 TB/Month
Recent Changes:
Immutable Snapshot Policy Enabled
Retention Increased from 14 Days to 365 Days
Ransomware Protection Policy Applied
Which THREE conclusions are supported by the available telemetry? (Choose 3.)
HPE0-J82 Exam Question 28
A Chief Infrastructure Architect is evaluating a final target-state architecture.
Proposed Environment:
HPE GreenLake for Block Storage
HPE Alletra Storage MP
InfoSight Analytics
StoreOnce Immutable Backups
Multi-Site Replication
QoS-Based Workload Segmentation
Business Objectives:
Improve cyber resiliency
Reduce operational complexity
Maintain enterprise SLAs
Improve capacity forecasting
Transition toward an OpEx model
Which THREE elements most directly contribute to achieving the stated objectives? (Choose 3.)
Proposed Environment:
HPE GreenLake for Block Storage
HPE Alletra Storage MP
InfoSight Analytics
StoreOnce Immutable Backups
Multi-Site Replication
QoS-Based Workload Segmentation
Business Objectives:
Improve cyber resiliency
Reduce operational complexity
Maintain enterprise SLAs
Improve capacity forecasting
Transition toward an OpEx model
Which THREE elements most directly contribute to achieving the stated objectives? (Choose 3.)
HPE0-J82 Exam Question 29
A customer is reviewing a ransomware protection architecture.
Current Design:
Snapshots: Every 15 minutes
Retention: 30 days
Replication: Daily
StoreOnce: Standard Backup Repository
Business Requirement:
"No administrator should be capable of deleting all recovery points."
Which THREE recommendations should be implemented? (Choose 3.)
Current Design:
Snapshots: Every 15 minutes
Retention: 30 days
Replication: Daily
StoreOnce: Standard Backup Repository
Business Requirement:
"No administrator should be capable of deleting all recovery points."
Which THREE recommendations should be implemented? (Choose 3.)
HPE0-J82 Exam Question 30
A SAN Network Engineer is tasked with deploying an NVMe over Fabrics (NVMe-oF) solution for a customer. The customer refuses to upgrade their existing, standard 10GbE and 25GbE Top-of- Rack (ToR) switches, which explicitly lack support for Data Center Bridging (DCB) and Priority Flow Control (PFC).
[Switch Configuration Extract]
Switch Model: Standard Layer 2/3 25GbE
DCBX State: Disabled/Unsupported
PFC State: Disabled/Unsupported
Which NVMe-oF transport protocol MUST the engineer select to successfully deploy this solution over the customer's existing, unupgraded network?
[Switch Configuration Extract]
Switch Model: Standard Layer 2/3 25GbE
DCBX State: Disabled/Unsupported
PFC State: Disabled/Unsupported
Which NVMe-oF transport protocol MUST the engineer select to successfully deploy this solution over the customer's existing, unupgraded network?