HPE0-J82 Exam Question 31
A Storage Administrator is evaluating a proposed lifecycle management policy for an object storage platform.
Configuration:
Versioning Enabled
Transition Non-Current Versions After 30 Days
Archive Non-Current Versions After 90 Days
Delete Non-Current Versions After 7 Years
Compliance Requirements:
Historical recovery capability
Long-term retention
Reduced storage cost
Which THREE outcomes should be expected? (Choose 3.)
Configuration:
Versioning Enabled
Transition Non-Current Versions After 30 Days
Archive Non-Current Versions After 90 Days
Delete Non-Current Versions After 7 Years
Compliance Requirements:
Historical recovery capability
Long-term retention
Reduced storage cost
Which THREE outcomes should be expected? (Choose 3.)
HPE0-J82 Exam Question 32
A customer plans to deploy NVMe-oF connectivity for a new high-performance analytics environment.
Current Network Infrastructure:
25Gb Ethernet
Standard Layer-3 switching
No DCB
No PFC
No planned network upgrades
Which THREE conclusions are most appropriate? (Choose 3.)
Current Network Infrastructure:
25Gb Ethernet
Standard Layer-3 switching
No DCB
No PFC
No planned network upgrades
Which THREE conclusions are most appropriate? (Choose 3.)
HPE0-J82 Exam Question 33
A Global Manufacturing Enterprise is evaluating a complete storage refresh strategy. The organization currently operates four independent storage arrays supporting:
SAP HANA Production
Oracle RAC Databases
VMware Production Clusters
VDI Infrastructure
Assessment Findings:
Current Peak IOPS: 420,000
Current Physical Capacity: 520 TB
Current Logical Capacity: 2.4 PB
Annual Growth Rate: 28%
Business Objectives:
Reduce operational complexity
Consolidate management tools
Improve cyber resiliency
Move from CapEx to OpEx
Maintain Tier-0 application SLAs
The proposed solution is HPE GreenLake for Block Storage with HPE Alletra Storage MP.
Which THREE recommendations best align with the customer's business and technical objectives? (Choose 3.)
SAP HANA Production
Oracle RAC Databases
VMware Production Clusters
VDI Infrastructure
Assessment Findings:
Current Peak IOPS: 420,000
Current Physical Capacity: 520 TB
Current Logical Capacity: 2.4 PB
Annual Growth Rate: 28%
Business Objectives:
Reduce operational complexity
Consolidate management tools
Improve cyber resiliency
Move from CapEx to OpEx
Maintain Tier-0 application SLAs
The proposed solution is HPE GreenLake for Block Storage with HPE Alletra Storage MP.
Which THREE recommendations best align with the customer's business and technical objectives? (Choose 3.)
HPE0-J82 Exam Question 34
A customer is evaluating HPE GreenLake for File Storage for an AI training platform.
Application Requirements:
Linux compute cluster
15 PB of unstructured training data
POSIX compliance
Multi-GB/s throughput per node
Minimal application modifications
Which THREE architectural statements are accurate? (Choose 3.)
Application Requirements:
Linux compute cluster
15 PB of unstructured training data
POSIX compliance
Multi-GB/s throughput per node
Minimal application modifications
Which THREE architectural statements are accurate? (Choose 3.)
HPE0-J82 Exam Question 35
A Storage Operations Team receives a predictive capacity alert.
[InfoSight Capacity Forecast]
Physical Capacity Used: 440 TB
Physical Capacity Free: 20 TB
Forecasted Exhaustion: 18 Days
Application Growth: 0.8 TB/month
Snapshot Growth: 22 TB/month
Recent Configuration Changes:
Immutable snapshots enabled
Snapshot retention increased from 14 days to 365 days
Which THREE conclusions are most appropriate? (Choose 3.)
[InfoSight Capacity Forecast]
Physical Capacity Used: 440 TB
Physical Capacity Free: 20 TB
Forecasted Exhaustion: 18 Days
Application Growth: 0.8 TB/month
Snapshot Growth: 22 TB/month
Recent Configuration Changes:
Immutable snapshots enabled
Snapshot retention increased from 14 days to 365 days
Which THREE conclusions are most appropriate? (Choose 3.)