HPE6-A47 Exam Question 46
Refer to the exhibit.

The exhibit shows the current plan for a wired network upgrade.
As much as possible, the customer wants to flatten the architecture and avoid recabling. However, each Building 2 switch must also maintain connectivity to the core if one link fails. What should the architect propose to meet the customer requirements?

The exhibit shows the current plan for a wired network upgrade.
As much as possible, the customer wants to flatten the architecture and avoid recabling. However, each Building 2 switch must also maintain connectivity to the core if one link fails. What should the architect propose to meet the customer requirements?
HPE6-A47 Exam Question 47
Refer to the exhibit.

A customer wants to replace the core and aggregation layer of an existing network. Currently the network routes between the aggregation layer and core, and uses the technologies shown in the exhibit.
The customer now wants to route at the core, instead of the aggregation layer, and extend some of the same VLANs in different buildings. However, the customer cannot eliminate the aggregation layer at this point.
What should the architect recommend?

A customer wants to replace the core and aggregation layer of an existing network. Currently the network routes between the aggregation layer and core, and uses the technologies shown in the exhibit.
The customer now wants to route at the core, instead of the aggregation layer, and extend some of the same VLANs in different buildings. However, the customer cannot eliminate the aggregation layer at this point.
What should the architect recommend?
HPE6-A47 Exam Question 48
An architect proposes an Aruba wireless solution for a customer that uses Microsoft Skype for Business. What should be set up on the MCs, or MM, to ensure that wireless voice traffic is properly prioritized?
HPE6-A47 Exam Question 49
Refer to the exhibit.

An architect needs to plan a network solution for a new office building with four floors. Each floor has two wiring closets with the equipment shown in the exhibit.
The switches will connect to employee desktops, a few campus APs controlled by MCs, and printers. The switches do not implement tunneled node.
What is a best practice design for the VLANs and subnets for the wired devices?

An architect needs to plan a network solution for a new office building with four floors. Each floor has two wiring closets with the equipment shown in the exhibit.
The switches will connect to employee desktops, a few campus APs controlled by MCs, and printers. The switches do not implement tunneled node.
What is a best practice design for the VLANs and subnets for the wired devices?
HPE6-A47 Exam Question 50
An architect needs to plan the RF coverage. Which application has the greatest potential impact on RF design?