CRISC Exam Question 41
Which of the following is the PRIMARY reason to use key control indicators (KCIs) to evaluate control operating effectiveness?
CRISC Exam Question 42
Ben is the project manager of the CMH Project for his organization. He has identified a risk that has a low probability of happening, but the impact of the risk event could save the project and the organization with a significant amount of capital. Ben assigns Laura to the risk event and instructs her to research the time, cost, and method to improve the probability of the positive risk event. Ben then communicates the risk event and response to management. What risk response has been used here?
CRISC Exam Question 43
An organization has outsourced a critical process involving highly regulated data to a third party with servers located in a foreign country. Who is accountable for the confidentiality of this data?
CRISC Exam Question 44
Which of the following will BEST help an organization evaluate the control environment of several third-party vendors?
CRISC Exam Question 45
Which of the following BEST protects an organization against breaches when using a software as a service (SaaS) application?