CRISC Exam Question 451
Shawn is the project manager of the HWT project. In this project Shawn's team reports that they have found a way to complete the project work cheaply than what was originally estimated earlier. The project team presents a new software that will help to automate the project work. While the software and the associated training costs $25,000 it will save the project nearly $65,000 in total costs. Shawn agrees to the software and changes the project management plan accordingly. What type of risk response had been used by him?
CRISC Exam Question 452
After identifying new risk events during a project, the project manager s NEXT step should be to:
CRISC Exam Question 453
Which of the following would BEST indicate to senior management that IT processes are improving?
CRISC Exam Question 454
Which of the following is true for Cost Performance Index (CPI)?
CRISC Exam Question 455
The BEST indication that risk management is effective is when risk has been reduced to meet: