CRISC Exam Question 631
The FIRST task when developing a business continuity plan should be to:
Correct Answer: B
A business continuity plan (BCP) is a system of prevention and recovery from potential threats to a company. The plan ensures that personnel and assets are protected and are able to function quickly in the event of a disaster1. The first task when developing a BCP should be to identify critical business functions and resources, because this will help to determine the scope, objectives, and priorities of the plan. Critical business functions and resources are those that are essential for the continuity of the company's operations, and that would cause significant disruption or damage if they were interrupted or lost. By identifying critical business functions and resources, the company can focus its efforts and resources on protecting and restoring them, and minimizing the impact of a disaster. The other options are not the first task when developing a BCP, because they depend on the identification of critical business functions and resources, as explained below:
A: Determine data backup and recovery availability at an alternate site is a task that relates to the recovery strategy of the BCP, which aims to restore the data and information systems that support the critical business functions and resources. However, this task cannot be performed without first identifying which data and information systems are critical, and what level of availability and recovery they require.
C: Define roles and responsibilities for implementation is a task that relates to the organization and governance of the BCP, which aims to assign and communicate the duties and expectations of the personnel involved in the plan. However, this task cannot be performed without first identifying which personnel are critical, and what functions and resources they are responsible for.
D: Identify recovery time objectives (RTOs) for critical business applications is a task that relates to the analysis and evaluation of the BCP, which aims to measure the acceptable downtime and recovery speed of the critical business functions and resources. However, this task cannot be performed without first identifying which business applications are critical, and what impact and likelihood they have. References = Risk and Information Systems Control Study Manual, Chapter 4, Section 4.2.1, page 115. What Is a Business Continuity Plan (BCP), and How Does It Work?, Business continuity plan (BCP) in 8 steps, with templates | BDC.ca, How Develop a Business Continuity Plan - Invenio IT, Business Continuity Planning | Ready.
gov, Develop a Robust Business Continuity Plan | Wrike
A: Determine data backup and recovery availability at an alternate site is a task that relates to the recovery strategy of the BCP, which aims to restore the data and information systems that support the critical business functions and resources. However, this task cannot be performed without first identifying which data and information systems are critical, and what level of availability and recovery they require.
C: Define roles and responsibilities for implementation is a task that relates to the organization and governance of the BCP, which aims to assign and communicate the duties and expectations of the personnel involved in the plan. However, this task cannot be performed without first identifying which personnel are critical, and what functions and resources they are responsible for.
D: Identify recovery time objectives (RTOs) for critical business applications is a task that relates to the analysis and evaluation of the BCP, which aims to measure the acceptable downtime and recovery speed of the critical business functions and resources. However, this task cannot be performed without first identifying which business applications are critical, and what impact and likelihood they have. References = Risk and Information Systems Control Study Manual, Chapter 4, Section 4.2.1, page 115. What Is a Business Continuity Plan (BCP), and How Does It Work?, Business continuity plan (BCP) in 8 steps, with templates | BDC.ca, How Develop a Business Continuity Plan - Invenio IT, Business Continuity Planning | Ready.
gov, Develop a Robust Business Continuity Plan | Wrike
CRISC Exam Question 632
Risk acceptance of an exception to a security control would MOST likely be justified when:
Correct Answer: B
The most likely justification for risk acceptance of an exception to a security control is when the business benefits exceed the loss exposure. Risk acceptance is a risk response strategy that involves acknowledging and tolerating the risk, without taking any action to reduce or transfer the risk. An exception to a security control is a deviation or non-compliance from the established security policy or standard, due to a valid business reason or circumstance. Risk acceptance of an exception to a security control may be justified when the business benefits exceed the loss exposure, which means that the value or advantage of the exception outweighs the potential cost or harm of the risk. For example, an exception to a security control may enable faster or easier access to the system or data, which may improve the productivity, efficiency, or satisfaction of the users or customers, and generate more revenue or profit for the business. The business benefits of the exception may exceed the loss exposure of the risk, which may be low or negligible, or may be mitigated by other controls or factors. Therefore, risk acceptance of an exception to a security control may be a reasonable and rational decision, based on the cost-benefit analysis of the exception and the risk. Automation cannot be applied to the control, the end-user license agreement has expired, and the control is difficult to enforce in practice are not the most likely justifications for risk acceptance of an exception to a security control, as they are either irrelevant or insufficient reasons, and they do not consider the business benefits or the loss exposure of the exception and the risk. References = CRISC Review Manual, 6th Edition, ISACA, 2015, page 50.
CRISC Exam Question 633
Senior management has requested more information regarding the risk associated with introducing a new application into the environment. Which of the following should be done FIRST?
Correct Answer: B
Understanding Risk Analysis:
* Risk analysis involves identifying potential risks associated with a new application and assessing their likelihood and impact on the organization.
* It provides a detailed understanding of the potential threats, vulnerabilities, and consequences, enabling informed decision-making.
Steps in Conducting a Risk Analysis:
* Identify Risks: Determine what risks could arise from the new application, including security vulnerabilities, compliance issues, and operational disruptions.
* Assess Risks: Evaluate the likelihood and impact of each identified risk. This includes both qualitative and quantitative assessments.
* Prioritize Risks: Rank the risks based on their assessed impact and likelihood to focus on the most significant threats first.
Importance of Risk Analysis:
* Provides senior management with a comprehensive view of the risks involved, enabling them to make informed decisions about proceeding with the application.
* Helps in developing mitigation strategies to address the identified risks.
Comparing Other Options:
* Perform an Audit: Audits are useful for evaluating existing controls but are not the first step in assessing risks for a new application.
* Develop Risk Scenarios: This is part of the risk analysis process but comes after identifying and assessing risks.
* Perform a Cost-Benefit Analysis: Important for decision-making but follows the initial risk analysis to understand potential impacts.
References:
* The CRISC Review Manual emphasizes the importance of conducting a risk analysis to understand and manage risks associated with new applications (CRISC Review Manual, Chapter 2: IT Risk Assessment, Section 2.2.1 Conducting Risk Analysis).
* Risk analysis involves identifying potential risks associated with a new application and assessing their likelihood and impact on the organization.
* It provides a detailed understanding of the potential threats, vulnerabilities, and consequences, enabling informed decision-making.
Steps in Conducting a Risk Analysis:
* Identify Risks: Determine what risks could arise from the new application, including security vulnerabilities, compliance issues, and operational disruptions.
* Assess Risks: Evaluate the likelihood and impact of each identified risk. This includes both qualitative and quantitative assessments.
* Prioritize Risks: Rank the risks based on their assessed impact and likelihood to focus on the most significant threats first.
Importance of Risk Analysis:
* Provides senior management with a comprehensive view of the risks involved, enabling them to make informed decisions about proceeding with the application.
* Helps in developing mitigation strategies to address the identified risks.
Comparing Other Options:
* Perform an Audit: Audits are useful for evaluating existing controls but are not the first step in assessing risks for a new application.
* Develop Risk Scenarios: This is part of the risk analysis process but comes after identifying and assessing risks.
* Perform a Cost-Benefit Analysis: Important for decision-making but follows the initial risk analysis to understand potential impacts.
References:
* The CRISC Review Manual emphasizes the importance of conducting a risk analysis to understand and manage risks associated with new applications (CRISC Review Manual, Chapter 2: IT Risk Assessment, Section 2.2.1 Conducting Risk Analysis).
CRISC Exam Question 634
Which of the following activities should be performed FIRST when establishing IT risk management processes?
Correct Answer: D
According to the Guide to Implementing an IT Risk Management Framework, the first activity that should be performed when establishing IT risk management processes is to assess the goals and culture of the organization. This is because the goals and culture of the organization define the context and scope of the IT risk management process, and influence the risk appetite and tolerance of the organization. By assessing the goals and culture of the organization, the IT risk manager can align the IT risk management process with the organization's strategy, vision, mission, values, and objectives. The IT risk manager can also identify the key stakeholders, roles, and responsibilities involved in the IT risk management process, and ensure that they have the necessary skills, knowledge, and resources to perform their tasks effectively. Additionally, the IT risk manager can establish the communication and reporting mechanisms for the IT risk management process, and ensure that they are consistent with the organization's culture and expectations. References = Guide to Implementing an IT Risk Management Framework, An Overview of the Risk Management Process
CRISC Exam Question 635
Which of the following is MOST important when developing key risk indicators (KRIs)?
Correct Answer: C
The most important factor when developing key risk indicators (KRIs) is to properly set thresholds, which are the predefined values or ranges that indicate the acceptable or unacceptable level of risk1. Thresholds can help to:
Trigger alerts or actions when the risk level exceeds or falls below the threshold, and enable timely and appropriate risk responses2.
Measure and monitor the performance and effectiveness of the risk responses, and ensure that the residual risk is within the risk appetite and tolerance3.
Communicate and report the risk status and performance to the stakeholders, and facilitate the decision- making and accountability for the risk management4.
The other factors are not the most important when developing KRIs, because:
Alignment with regulatory requirements is a necessary but not sufficient factor when developing KRIs, as it ensures that the KRIs comply with the applicable laws, rules, or standards that govern the organization's activities and operations5. However, alignment with regulatory requirements does not guarantee that the KRIs are relevant and useful for the organization's specific risk profile and objectives.
Availability of qualitative data is a desirable but not essential factor when developing KRIs, as it provides additional information or insights that may not be captured by quantitative data, such as opinions, perceptions, or feedback. However, availability of qualitative data does not ensure that the KRIs are reliable and consistent, as qualitative data may be subjective and difficult to measure and compare.
Alignment with industry benchmarks is a useful but not critical factor when developing KRIs, as it provides a reference or a standard for comparing the organization's risk level and performance with its peers or competitors. However, alignment with industry benchmarks does not ensure that the KRIs are suitable and feasible for the organization's specific context and capabilities.
References =
Threshold - CIO Wiki
Risk Thresholds: How to Set Them and When to Use Them - ProjectManager.com Risk Appetite and Tolerance - CIO Wiki Risk Reporting - CIO Wiki Regulatory Compliance - CIO Wiki
[Regulatory Risk - CIO Wiki]
[Qualitative Data - CIO Wiki
Trigger alerts or actions when the risk level exceeds or falls below the threshold, and enable timely and appropriate risk responses2.
Measure and monitor the performance and effectiveness of the risk responses, and ensure that the residual risk is within the risk appetite and tolerance3.
Communicate and report the risk status and performance to the stakeholders, and facilitate the decision- making and accountability for the risk management4.
The other factors are not the most important when developing KRIs, because:
Alignment with regulatory requirements is a necessary but not sufficient factor when developing KRIs, as it ensures that the KRIs comply with the applicable laws, rules, or standards that govern the organization's activities and operations5. However, alignment with regulatory requirements does not guarantee that the KRIs are relevant and useful for the organization's specific risk profile and objectives.
Availability of qualitative data is a desirable but not essential factor when developing KRIs, as it provides additional information or insights that may not be captured by quantitative data, such as opinions, perceptions, or feedback. However, availability of qualitative data does not ensure that the KRIs are reliable and consistent, as qualitative data may be subjective and difficult to measure and compare.
Alignment with industry benchmarks is a useful but not critical factor when developing KRIs, as it provides a reference or a standard for comparing the organization's risk level and performance with its peers or competitors. However, alignment with industry benchmarks does not ensure that the KRIs are suitable and feasible for the organization's specific context and capabilities.
References =
Threshold - CIO Wiki
Risk Thresholds: How to Set Them and When to Use Them - ProjectManager.com Risk Appetite and Tolerance - CIO Wiki Risk Reporting - CIO Wiki Regulatory Compliance - CIO Wiki
[Regulatory Risk - CIO Wiki]
[Qualitative Data - CIO Wiki
- Other Version
- 1817ISACA.CRISC.v2026-07-15.q907
- 2226ISACA.CRISC.v2026-03-31.q857
- 2586ISACA.CRISC.v2026-01-15.q649
- 4701ISACA.CRISC.v2025-08-27.q675
- 6753ISACA.CRISC.v2025-01-04.q999
- 3455ISACA.CRISC.v2024-06-13.q683
- 4721ISACA.CRISC.v2024-04-02.q999
- 4461ISACA.CRISC.v2023-07-10.q544
- 6970ISACA.CRISC.v2022-05-25.q338
- 76ISACA.Actual4dump.CRISC.v2022-04-12.by.newman.349q.pdf
- 6620ISACA.CRISC.v2022-02-22.q349
- 6831ISACA.CRISC.v2021-10-27.q295
- 42ISACA.Updatedumps.CRISC.v2021-09-05.by.bonnie.114q.pdf
- Latest Upload
- 179Microsoft.AI-300.v2026-08-08.q76
- 136Splunk.SPLK-1004.v2026-08-08.q55
- 121Oracle.1Z0-1075-26.v2026-08-08.q22
- 128VMware.3V0-21.25.v2026-08-08.q35
- 205APICS.CPIM-8.0.v2026-08-08.q264
- 183Cisco.300-720.v2026-08-08.q115
- 150Splunk.SPLK-1003.v2026-08-08.q94
- 143ISACA.AAIR.v2026-08-07.q41
- 132Microsoft.70-123.v2026-08-07.q37
- 148AMP.CRL.v2026-08-07.q61
[×]
Download PDF File
Enter your email address to download ISACA.CRISC.v2025-09-26.q726 Practice Test