Which of the following metrics is MOST LIKELY to trigger a control directive to increase test execution resources?
You are a Test Manager and have started a program of test process improvement. You are following the IDEAL model and have completed the first three phases, now you are ready to go further. Which TWO of the following activities will enable you to complete the remaining phases of the IDEAL model?
You are writing a system test level plan and are defining the test activities that must take place during test implementation. There is an established project risk register in place, with product risks addressing all new features to be developed. Three time-boxed cycles of system test execution are planned, and all the new features will be delivered in the first cycle.
The project test strategy states that the stakeholders require an overall view of the product quality for these features. This should be achieved by planning to test each product risk, to some degree, during the first cycle of test execution.
Which risk-based mitigation approach should be adopted during test implementation, to BEST meet the stakeholders' requirement?
You are the Test Manager for a critical system and are using a risk-based approach for this project.
Which of the following would most clearly convey the current status to project stakeholders? [3]
Your company just won a contract to create a new sales application and has committed to a very aggressive delivery timeline. Due to the quick turnaround your primary stakeholder wants to be heavily involved in the design and is very anxious to see the outcome. Because of this, your company has decided to use a spiral development approach. You have a defined test policy and typically use an analytical approach to testing, however, this approach will not work with the development approach.
What test strategy should be utilized?