CTAL-TM_Syll2012 Exam Question 61

Test Management
Assume you have some data related to confirmation testing during system testing of a past project.
In that project 240 bug reports have been opened once, 80 were opened twice, 10 were opened three times and no bug reports have been opened more than three times.
You estimate that a bug report, which has failed its confirmation test, costs, on average, 3 person-hours.
Which of the following statements correctly describe the value of these confirmatory testing activities based on cost of quality?
Number of correct responses: 1
K3 2 credits
  • CTAL-TM_Syll2012 Exam Question 62

    Test Management
    Which of the following statements, about the test reporting activities for a project adopting an iterative lifecycle model with very short iterations (e.g. two weeks iterations), is correct?
  • CTAL-TM_Syll2012 Exam Question 63

    Test Management
    You are the Test Manager of a new project aimed at developing a software system that must be certified at level B of the DO-178B standard. The project will follow a V-Model software development life cycle and it will have four formal levels of testing: component, integration, system and acceptance testing.
    You must produce the test plan documentation for this project by providing an adequate coordination across the four levels of testing in order to assure auditability.
    Which of the following answers would you expect to best describe how to organize the test plan?
  • CTAL-TM_Syll2012 Exam Question 64

    You are the Test Manager on a project following an iterative life-cycle model. The project should consist of nine iterations of one month duration each. It is planned to develop the most important features to have a stable core of the application in the first three iterations and to add the additional features in the last six iterations.
    At the beginning of the first iteration, only a draft version of the requirements specification document for the core features is available. Assume that during each of the first three iterations, the chosen features are fully completed and unit tested.
    Which of the following statements is true in this context?
    K4 3 credits
  • CTAL-TM_Syll2012 Exam Question 65

    Test Management
    Which of the following answers describes a factor that may reduce the effort spent when using distributed test teams without negatively affecting system quality?
    Number of correct responses: 1
    K2 1 credit