Question 1

As the Test Manager for an agile project how would you BEST plan and guide the testing activities during development? SELECT ONE OPTION

Question 2

You are a newly appointed Test Manager in an organisation that has no separate test team, no formal testing process and testing is considered to be, at best, ad-hoc in approach. The IT director is keen to introduce improvement across all areas of the organisation, not just testing. This is so that the current level of maturity can be assessed and roadmaps outlined for improving processes in a staged way. He has asked you to recommend a test process improvement model and you have suggested TMMi.
Which ONE of the following is a valid reason for your recommendation? SELECT ONE OPTION

Question 3

You have been carefully monitoring the progress of testing for your project. You have been using the established traceability to verify that the requirements and test conditions are being adequately addressed. The test team is proceeding well in their test case execution and you can see that you are achieving about 80% coverage of the test conditions per the traceability mapping in your test management system. You have seen a number of defects being logged against test conditions that are failing, but you do not see a mapping of the test cases to those conditions.
What is likely to be occurring in the testing area that is causing the traceability to break down? [2]

Question 4

You just handed over the Defect Accepted and Deferred report to your Maintenance team.
Which testing activity are you performing? [1]

Question 5

A car rental company offers discounts to its customers based on a number of factors, including booking history, length of membership and type of car being booked. An update to the rental application is under test, with test cases written that specifically address a documented product risk covering discount calculation.
Although the risk impact was analysed as high, the likelihood was given as low, as there had been no known changes to the calculation rules. However, during test execution some discount calculations were incorrect and investigation showed that code changes had been made that impacted the discount algorithms. As a result, the likelihood was increased to high by the risk management team.
Which would be the BEST measure to take to respond to the current situation?