(Under the FIDIC Red, Yellow, and Silver Books (1999 editions), the Engineer/Employer shall be entitled to withhold from the release of retention money the estimated cost of any work which remains to be executed under Clause 11 (Defects Liability) in the Red Book or under Clause 12 (Tests after Completion) in the Yellow and Silver Books. Is this statement true or false?)
(Under the FIDIC Red, Yellow, and Silver Books (both editions), the Contractor has a contractual obligation to give notice to the Employer if it discovers errors or defects of a technical nature. Is this statement true or false?)
Which one of the following statements is NOT correct in respect of FIDIC Yellow Book (both editions)?
(You are the Contract Manager of the Employer ' s Representative for a project using FIDIC Silver Book (edition 1999). The Contract Agreement does not define the Commencement Date. The Contract has been legally effective for 4 weeks. You are writing a letter urging the Employer to issue a Notice of Commencement Date. Why is this important? (2 correct answers apply))